Tierra Group served as the Lead Auditor and conducted MARs for the TSFs at this confidential project. Tierra Group reviewed all available facility documentation, including OMS Manuals, EAPs, design reports, As-Built Reports, annual inspection reports, and other relevant documentation in determining each site’s compliance with the Company’s Tailings and Heap Leach Management Standard.

Independent Engineer's Review

Tierra Group personnel served as the Audit Lead to review tailings management procedures and compared them to standards outlined in the Company’s Corporate Tailings and Heap Leach Management Standard.

Tailings Assurance Audit

Tierra Group completed a Tailings Assurance Audit (TAA) for Tailings Storage Facility 2 (TSF2). The TAA was completed to ensure the TSF and site operations complied with the Company’s Tailings Management Standard, which closely mirrors Global Industry Standard on Tailings Management (GISTM) requirements. 

Project Highlights:

  • Independent Engineering Review
  • Tailings Storage Facilities
  • Tailings Assurance Audit

Similar projects

Mission Mine

Tierra Group is implementing a corporate Tailings Stewardship Strategy (TSS) at all of ASARCO Grupo Mexico’s mines in Arizona, USA (Hayden, Mission and Ray mines). Tierra Group conducted a site visit to each site to perform dam safety inspections, interview…

VIEW PROJECT

Camino Rojo

Heap Leach Procurement & Construction Quality Assurance Tierra Group provided Issued for Construction (IFC) design drawings and specifications for procurement requirements for the expansion of the Camino Rojo HLF. Information required included liner specifications, drainage collection piping, and quantities. Additionally,…

VIEW PROJECT

Lost Creek Project | USA

Tierra Group is assisting Millcreek Mining and Black Mountain Sand with the preparation of permitting documents for the Lost Creek Project; including a preliminary Stormwater Management Plan, preliminary Groundwater Monitoring Plan, and general permitting exhibits. Tierra Group conducted a site geotechnical…

VIEW PROJECT

Jaguar Mines

Jaguar's gold operations, Turmalina, Paciência and Caeté, are located in the Iron Quadrangle region, a prolific greenstone belt near the city of Belo Horizonte in the state of Minas Gerais, Brazil. Jaguar controls 27,357 hectares of mineral concessions in this…

VIEW PROJECT

Dam Low Level Outlet Replacement

Tierra Group completed a geotechnical investigation, which included overseeing hollow stem auger (HSA) drilling and laboratory testing, that characterized the existing earthen dam. Tierra Group completed a low-level outlet structure design that was believed to have been compromised by internal…

VIEW PROJECT

Boleo Mine

Tierra Group performed an independent technical peer review of the Boleo Mine’s operating tailings storage facility design. In doing so Tierra Group identified several design modifications that when implemented for future stages will reduce sustaining capital cost expenditures by several…

VIEW PROJECT

Quinsam Coal

Tierra Group served as an independent subject matter expert for the Quinsam Coal Corporation (QCC) Independent Tailings Review Board (ITRB) in British Columbia, Canada. The annual review process included review of existing documents, a site visit, and collaborative meetings with…

VIEW PROJECT

El Mochito Mine

El Mochito is an underground zinc/silver mine located in the Santa Barbara Mountains in north-central Honduras. Tierra Group’s Team has been providing Tailings Stewardship Services at El Mochito continuously for the past 26 years. Since 1989, Tierra Group engineers have provided…

VIEW PROJECT

Pierina Mine

Barrick Gold Corporation’s Pierina Mine in Ancash Department, Perú began operations in 1998. A progressive reclamation and closure plan began in 2013.  In 2015-16 Tierra Group developed detailed engineering designs for channels, sediment traps, two 45,000 m3 sediment ponds, water…

VIEW PROJECT

Tonopah Flats | Tailings Storage Facility

Tierra Group assisted with developing tailings disposal alternatives.

VIEW PROJECT

Bolivar Mine

The Bolivar mine is a 3,000 tonne per day underground mining operation in Chihuahua, Mexico producing copper, zinc, silver, and gold. Space constraints in mountainous terrain require dewatering tailings to reduce required area for tailings storage. Tierra Group is assisting…

VIEW PROJECT

El Cubo

Tierra Group provided Tailings Stewardship Services including a dam inspection, slope stability analysis review and operational improvements for Endeavour Silver’s El Cubo tailings storage facility in Guanajuato, Mexico.