
Barrick Gold Corporation’s Pierina Mine in Ancash Department, Perú began operations in 1998. A progressive reclamation and closure plan began in 2013. In 2015-16 Tierra Group developed detailed engineering designs for channels, sediment traps, two 45,000 m3 sediment ponds, water energy dissipation structures, and an automatized mechanical-electrical water and sediment pumping system.
Robinson Mine Tailings Impoundment Audit Prior to joining Tierra Group, our Team completed a third-party tailings impoundment audit. The audit included reviewing operational procedures, monitoring, design, and future tailings storage planning. Produced an audit report for company’s internal use. (Tetra Tech,…
Tierra Group provided Tailings Stewardship Services for TSFs and water dams at the Cadia, Terfer, and Red Chris properties. Responsibilities included data/report review; identifying and assisting the client with managing risks, liabilities, controls, and reporting; evaluating progress towards GISTM compliance;…
Tierra Group prepared a Heap Leach Facility (HLF) design to an FS level, including a geotechnical investigation, HLF design basis and criteria, hydrology and water balance, geotechnical engineering analysis, specifications, material quantities, and design report. In addition, Tierra Group prepared…
Hydrogeologic Characterization Tierra Group provided hydrogeological support for data characterization and developed a conceptual and groundwater model to evaluate mine water inflows and the associated groundwater drawdown due to mine dewatering activities. Water Management Technical Review Tierra Group provided a…
Dry Stack Tailings Storage Facility Tierra Group designed a dry stack TSF to store excess tailings from the underground paste backfill. The dry stack TSF was challenging, given the limited land area, steep terrain, seasonal cold weather, and surface water…
Newmarket Gold’s Cosmo Howley Project Area (CHPA) is a gold mine in the Northern Territory (NT), Australia. An underground mine is currently in operation with planned underground expansion. CHPA contains several legacy open pits, waste rock dumps, and surface water…
Tierra Group completed a geotechnical investigation, which included overseeing hollow stem auger (HSA) drilling and laboratory testing, that characterized the existing earthen dam. Tierra Group completed a low-level outlet structure design that was believed to have been compromised by internal…
Tierra Group provided a Third-Party review of the Hermosa Project Tailings Storage Facility Design and Construction stages 1 & 2 in Patagonia, Arizona
Tierra Group began work at La Trinidad providing heap leach pad construction recommendations and a water balance. Tierra Group continued support with a heap leach pad expansion design, slope stability analyses, hydrologic analyses, diversion design, liner design, and leach solution…
Tierra Group provides Tailings Stewardship Services for the Marlin Mine Tailings Storage Facility. Tierra Group performed a 5-year Dam Safety Review consistent with the Canadian Dam Association protocols, a Facilitated Risk Assessment, site training and in depth inspections of management…
Tierra Group provided slope stability analysis for Agnico Eagle’s dry stack tailings storage facility containing 330,000 tonnes of tailings.
Tierra Group engineers designed La Esperanza TSF, a 2.1-km long, 35-m high, earthfill tailings dam with an HDPE lined impoundment footprint of 840,000 m2. Tierra Group designed and provided Construction Quality Assurance (CQA) for all subsequent downstream dam stages. Stage…










