Peñasquito

Project Highlights:

  • Tailings Stewardship Services

Tierra Group was selected to assist Goldcorp with global Tailings Stewardship Strategy (TSS) implementation at all of Goldcorp’s active tailings sites in Latin America (Mexico, Argentina, and Guatemala). Tierra Group worked in conjunction with Goldcorp and another global engineering consulting company (selected to implement the program in Canada) to develop a coordinated implementation and execution strategy for the TSS. Tierra Group personnel conducted multiple site visits to each site to perform dam safety inspections, interview operations staff, provide training for site operations personnel, and review each operation for conformance with BMPs for facility design, construction, operation, and closure. Work included conducting formal risk assessments with input from all of the various operations teams at each mine plus each facility’s EoR and corporate representatives to ensure all risks were identified and quantified into an overall site-wide risk register. Recommendations for mitigating risks at each site were provided in reports developed for each site.

Project Highlights:

  • Tailings Stewardship Services

Similar projects

Dam Low Level Outlet Replacement

Tierra Group completed a geotechnical investigation, which included overseeing hollow stem auger (HSA) drilling and laboratory testing, that characterized the existing earthen dam. Tierra Group completed a low-level outlet structure design that was believed to have been compromised by internal…

VIEW PROJECT

Tailings Assurance Audit | Canada

Tierra Group completed a Tailings Assurance Audit (TAA) for a closed Tailings Storage Facility (TSF). The TAA was completed to ensure the TSF and site operations complied with the Company's Tailings Management Standard, which closely mirrors Global Industry Standard on…

VIEW PROJECT

Contonga Mine

Contonga, a 990 tpd underground Zinc mine located in Perú’s Ancash Region, has been in operation for more than 25 years. Tierra Group team members assisted Nyrstar’s acquisition due diligence team by performing a fatal flaw analysis of Contonga’s Tucush…

VIEW PROJECT

Grupo Mexico | La Caridad

Tailings Storage Facility (TSF) AuditTierra Group performed the La Caridad TSF Audit. Tierra Group’s scope of work entailed a site visit, data review, dam safety inspection (DSI), site interviews, and best management practices training for operations personnel.

VIEW PROJECT

Black Butte Copper Project

Tierra Group performed an independent engineering design review of a Cemented Tailings Facility (CTF) and multiple processes and freshwater ponds. Tailings will be mixed with cement at the paste plant and deposited in the CTF along with underground mine development…

VIEW PROJECT

Candelones Oxide Project | Heap Leach Feasibility Design

Tierra Group prepared a Heap Leach Facility (HLF) design to an FS level, including a geotechnical investigation, HLF design basis and criteria, hydrology and water balance, geotechnical engineering analysis, specifications, material quantities, and design report. In addition, Tierra Group prepared…

VIEW PROJECT

Peñasquito

Tierra Group was selected to assist Goldcorp with global Tailings Stewardship Strategy (TSS) implementation at all of Goldcorp’s active tailings sites in Latin America (Mexico, Argentina, and Guatemala). Tierra Group worked in conjunction with Goldcorp and another global engineering consulting…

VIEW PROJECT

Aranzazú Mine

The Aranzazú Mine is a copper-gold-silver mine located in the northeastern region of Zacatecas, Mexico. The mine includes both open pit and underground operations. The mill currently processes 2,600 tonnes of ore per day. Tierra Group finalized the geotechnical investigation…

VIEW PROJECT

Newcrest Cadia Tailings Stewardship

Tierra Group provided Tailings Stewardship Services for TSFs and water dams at the Cadia, Terfer, and Red Chris properties. Responsibilities included data/report review; identifying and assisting the client with managing risks, liabilities, controls, and reporting; evaluating progress towards GISTM compliance;…

VIEW PROJECT

Robinson Mine

Robinson Mine Tailings Impoundment Audit Prior to joining Tierra Group, our Team completed a third-party tailings impoundment audit. The audit included reviewing operational procedures, monitoring, design, and future tailings storage planning. Produced an audit report for company’s internal use. (Tetra Tech,…

VIEW PROJECT

La India Mine

GoldSim Training Tierra Group provided GoldSim training to the Agnico Team and updated the heap leach water balance. Phase 2 & 3 Heap Leach Pad Design and Construction Quality Assurance Tierra Group provided engineering design services for the Phase 2 and 3…

VIEW PROJECT

Fire Creek Mine

Tierra Group conducted a siting analysis for a new WRSF to support the mine’s future production increase as part of the Preliminary Feasibility Study (PFS). In addition to supporting the PFS, Tierra Group assisted in preparing and submitting several engineering…