Isabella Pearl

Project Highlights:

  • Heap Leach Pad Design Peer Review
  • Slope Stability Analysis
  • Heap Leach Facility Expansion
  • Permitting Support
  • Geotechnical Investigation

Tierra Group performed a technical peer review of the Isabella Pearl heap leach facility (HLF) owned by Gold Resource Corporation. Isabella Pearl mine is located at the west end of the Santa Fe mining district in the Walker Lane gold belt about 6 miles northeast of Luning, Nevada, in Mineral County. The HLF will have a nominal throughput of 8,000 tons per day over a period of 15 months following of pre-production development and construction. Tierra Group performed the review with the following objectives:

  • Peer review the existing engineering design and drawings to ensure the proposed engineering design is adequate and in conformity with accepted engineering practices;
  • Identify opportunities to “optimize” the design to potentially reduce capital or operating costs; and
  • Identify associated risks (regulatory, financial, construction schedule, etc.) with implementing optimization.

Tierra Group identified a number of optimization opportunities and provided design enhancement recommendations to potentially reduce capital or operation costs.

Expansion Pit Slope Review

Tierra Group conducted an expansion pit slope review that included a technical memorandum of site observations/investigation, a review of past and new data, a basic slope analyses that developed recommendations for slope angles that determined if the Pit Expansion would be stable, and provided suggestions for a slope monitoring program.

HLF Phase 2A Engineering Design Change (EDC)

Tierra Group prepared an EDC to increase the permitted storage height of the existing HLF. A geotechnical field investigation and stability analysis for the Phase 2A and 3 expansion were also completed. Analysis results guided the civil grading and engineering design for each phase.

Project Highlights:

  • Heap Leach Pad Design Peer Review
  • Slope Stability Analysis
  • Heap Leach Facility Expansion
  • Permitting Support
  • Geotechnical Investigation

Similar projects

Karouni Mine

Tierra Group reviewed and provided pit slope recommendations and conducted hydrological assessments for the Resource 1 and 2 deposits water management system at Troy Resources’ Karouni Mine (Karouni). Advanced pre-feasibility level recommendations for pit development were provided based on benchmarking…

VIEW PROJECT

Turmalina Complex

Tierra Group developed a site-wide water management plan to improve operational water usage and management at Jaguar Mining's Turmalina Complex in Minas Gerais, Brazil. Turmalina is a zero-discharge facility that required optimizing tailings supernatant usage in the process, enhanced evaporation…

VIEW PROJECT

Don Mario Gold Mine

Don Mario Mine is an open pit gold/copper mine located in the Chiquitos Province, Santa Cruz, Bolivia that has been operating since 2002 and currently produces 2700 tpd mill throughput. Conventional tailings are transported and deposited in a high-density polyethylene lined geomembrane valley…

VIEW PROJECT

Çöpler Tailings Storage Facility and Heap Leach Facility Technical Review

Tierra Group has a history of annually providing third-party technical reviews for the tailings storage facility and heap leach facility at Anagold's Çöpler Gold Mine in Middle Anatolia, Turkey. Additionally, Tierra Group currently performs independent technical reviews for the rockfill…

VIEW PROJECT

Bolanitos

Tierra Group provided Tailings Stewardship Services including a dam inspection, slope stability analysis review and operational improvements for Endeavour Silver’s Bolanitos tailings storage facility.

VIEW PROJECT

Isabella Pearl

Tierra Group performed a technical peer review of the Isabella Pearl heap leach facility (HLF) owned by Gold Resource Corporation. Isabella Pearl mine is located at the west end of the Santa Fe mining district in the Walker Lane gold…

VIEW PROJECT

Mission Mine

Tierra Group is implementing a corporate Tailings Stewardship Strategy (TSS) at all of ASARCO Grupo Mexico’s mines in Arizona, USA (Hayden, Mission and Ray mines). Tierra Group conducted a site visit to each site to perform dam safety inspections, interview…

VIEW PROJECT

Topia Mine

Topia Mine Phases 1-3Tierra Group supervised the first 3 phases of Geologic Mapping and Instrumentation Installation and developed a Mechanically Stabilized Earth Wall Design at Great Panther Silver’s Topia Mine in Durango, Mexico.

VIEW PROJECT

Hollister Waste Rock Facility

Hollister Waste Rock Facility Storage Tierra Group performed a third-party peer review of a Waste Rock Storage Facility (WRSF) design at Klondex Mines’ (Klondex) Hollister Mine in northern Nevada. The WRSF, as designed, involved lining the mine’s existing West Pit…

VIEW PROJECT

Caeté Complex

Tierra Group developed a site-wide water management plan, and performed a liquefaction potential study following the Samarco tailings dam failure in Minas Gerais, Brazil. A tailings storage facility water balance was developed to optimize water usage and minimize risks at…

VIEW PROJECT

Los Gatos Project

TSF Design and CQA Tierra Group provided detailed Stage 1 and 2 Tailings Storage Facility design, conducted a process plant geotechnical foundation investigation, and provided Construction Quality Assurance for Sunshine Silver Mining's Los Gatos Project in Chihuahua, Mexico. Tierra Group then…

VIEW PROJECT

Sterling Mine

Sterling Mine is an underground gold mine in southern Nevada which recovers gold through heap leaching and a carbon adsorption-desorption-recovery (ADR) plant. Tierra Group team members have a long history at Sterling, starting with heap leach pad final permanent closure…

VIEW PROJECT