Isabella Pearl

Project Highlights:

  • Heap Leach Pad Design Peer Review
  • Slope Stability Analysis
  • Heap Leach Facility Expansion
  • Permitting Support
  • Geotechnical Investigation
  • Pit Slope Design
  • Geotechnical Modeling
  • Diversion Design
  • Hydrology/Hydraulics

Tierra Group performed a technical peer review of the Isabella Pearl heap leach facility (HLF) owned by Gold Resource Corporation. Isabella Pearl mine is located at the west end of the Santa Fe mining district in the Walker Lane gold belt about 6 miles northeast of Luning, Nevada, in Mineral County. The HLF will have a nominal throughput of 8,000 tons per day over a period of 15 months following of pre-production development and construction. Tierra Group performed the review with the following objectives:

  • Peer review the existing engineering design and drawings to ensure the proposed engineering design is adequate and in conformity with accepted engineering practices;
  • Identify opportunities to “optimize” the design to potentially reduce capital or operating costs; and
  • Identify associated risks (regulatory, financial, construction schedule, etc.) with implementing optimization.

Tierra Group identified a number of optimization opportunities and provided design enhancement recommendations to potentially reduce capital or operation costs.

Expansion Pit Slope Review

Tierra Group conducted an expansion pit slope review that included a technical memorandum of site observations/investigation, a review of past and new data, a basic slope analyses that developed recommendations for slope angles that determined if the Pit Expansion would be stable, and provided suggestions for a slope monitoring program.

HLF Phase 2A Engineering Design Change (EDC)

Tierra Group prepared an EDC to increase the permitted storage height of the existing HLF. A geotechnical field investigation and stability analysis for the Phase 2A and 3 expansion were also completed. Analysis results guided the civil grading and engineering design for each phase.

Crimson Preliminary Pit Slope Design

Tierra Group recommended a field investigation program and geotechnical modeling for the new Crimson Pit near the existing Isabella Pearl Pit. Tierra Group also provided preliminary pit slope design parameters.

Civit Cat Diversion

Tierra Group completed a diversion design to route stormwater around a planned open pit expansion. Tierra Group conducted hydrologic analyses to determine peak flows due to the 500-year 24‑hour rainfall event and completed the diversion’s civil and hydraulic design for permitting and construction. Challenges included steep topography and limiting rock excavation.

Project Highlights:

  • Heap Leach Pad Design Peer Review
  • Slope Stability Analysis
  • Heap Leach Facility Expansion
  • Permitting Support
  • Geotechnical Investigation
  • Pit Slope Design
  • Geotechnical Modeling
  • Diversion Design
  • Hydrology/Hydraulics

Similar projects

San Francisco Mine

Tierra Group conducted geo-electrical testing to locate leaks present in the geomembrane liners underlying a Solution Conveyance Canal, Sumps 1 and 2, and the Intermediate Pond at Timmins Gold Corp’s San Francisco Mine in Sonora, Mexico. Leak detection testing procedures…

VIEW PROJECT

Grupo Mexico | La Caridad

Tailings Storage Facility (TSF) AuditTierra Group performed the La Caridad TSF Audit. Tierra Group’s scope of work entailed a site visit, data review, dam safety inspection (DSI), site interviews, and best management practices training for operations personnel.

VIEW PROJECT

Mascota Mine

Creston Mascota Mine is located in Chihuahua, Mexico and is owned and operated by Agnico Eagle Mexico. Tierra Group designed the Phase 4 heap leach pad, buttress, which included geotechnical investigations, slope stability analyses and a water balance for Agnico…

VIEW PROJECT

Quinsam Coal

Tierra Group served as an independent subject matter expert for the Quinsam Coal Corporation (QCC) Independent Tailings Review Board (ITRB) in British Columbia, Canada. The annual review process included review of existing documents, a site visit, and collaborative meetings with…

VIEW PROJECT

Isabella Pearl

Tierra Group performed a technical peer review of the Isabella Pearl heap leach facility (HLF) owned by Gold Resource Corporation. Isabella Pearl mine is located at the west end of the Santa Fe mining district in the Walker Lane gold…

VIEW PROJECT

Midas Mine

The Midas Mine is located in northern Nevada, and is owned and operated by Hecla Mining Company.  The mine is an underground mine with an operating mill. The mine’s existing tailings facilities are nearing their end of operating life and…

VIEW PROJECT

Mexican Hat PEA Update

Tierra Group conducted an update of the Mexican Hat Project’s Preliminary Economic Assessment. Tierra Group’s update included the heap leach facility design and preliminary stacking plan, waste rock storage pad, and crushed rock storage pad design.

VIEW PROJECT

Lost Creek Project | USA

Tierra Group is assisting Millcreek Mining and Black Mountain Sand with the preparation of permitting documents for the Lost Creek Project; including a preliminary Stormwater Management Plan, preliminary Groundwater Monitoring Plan, and general permitting exhibits. Tierra Group conducted a site geotechnical…

VIEW PROJECT

La Caridad | Tailings Storage Facility Audit

Tierra Group performed the La Caridad TSF Audit. Tierra Group’s scope of work entailed a site visit, data review, dam safety inspection (DSI), site interviews, and provided best management practices training for operations personnel.

VIEW PROJECT

Morelos Mine

Tierra Group designed and implemented a stability and safety monitoring plan for Torex Gold’s Morelos Mine dry stack tailings storage facility (TSF). The monitoring plan includes installing inclinometers and vibrating wire piezometers, and training operations staff to download instrumentation readings.…

VIEW PROJECT

Robinson Mine

Robinson Mine Tailings Impoundment Audit Prior to joining Tierra Group, our Team completed a third-party tailings impoundment audit. The audit included reviewing operational procedures, monitoring, design, and future tailings storage planning. Produced an audit report for company’s internal use. (Tetra Tech,…

VIEW PROJECT

Dam Low Level Outlet Replacement

Tierra Group completed a geotechnical investigation, which included overseeing hollow stem auger (HSA) drilling and laboratory testing, that characterized the existing earthen dam. Tierra Group completed a low-level outlet structure design that was believed to have been compromised by internal…

VIEW PROJECT