Isabella Pearl

Project Highlights:

  • Heap Leach Pad Design Peer Review
  • Slope Stability Analysis
  • Heap Leach Facility Expansion
  • Permitting Support
  • Geotechnical Investigation
  • Pit Slope Design
  • Geotechnical Modeling
  • Diversion Design
  • Hydrology/Hydraulics

Tierra Group performed a technical peer review of the Isabella Pearl heap leach facility (HLF) owned by Gold Resource Corporation. Isabella Pearl mine is located at the west end of the Santa Fe mining district in the Walker Lane gold belt about 6 miles northeast of Luning, Nevada, in Mineral County. The HLF will have a nominal throughput of 8,000 tons per day over a period of 15 months following of pre-production development and construction. Tierra Group performed the review with the following objectives:

  • Peer review the existing engineering design and drawings to ensure the proposed engineering design is adequate and in conformity with accepted engineering practices;
  • Identify opportunities to “optimize” the design to potentially reduce capital or operating costs; and
  • Identify associated risks (regulatory, financial, construction schedule, etc.) with implementing optimization.

Tierra Group identified a number of optimization opportunities and provided design enhancement recommendations to potentially reduce capital or operation costs.

Expansion Pit Slope Review

Tierra Group conducted an expansion pit slope review that included a technical memorandum of site observations/investigation, a review of past and new data, a basic slope analyses that developed recommendations for slope angles that determined if the Pit Expansion would be stable, and provided suggestions for a slope monitoring program.

HLF Phase 2A Engineering Design Change (EDC)

Tierra Group prepared an EDC to increase the permitted storage height of the existing HLF. A geotechnical field investigation and stability analysis for the Phase 2A and 3 expansion were also completed. Analysis results guided the civil grading and engineering design for each phase.

Crimson Preliminary Pit Slope Design

Tierra Group recommended a field investigation program and geotechnical modeling for the new Crimson Pit near the existing Isabella Pearl Pit. Tierra Group also provided preliminary pit slope design parameters.

Civit Cat Diversion

Tierra Group completed a diversion design to route stormwater around a planned open pit expansion. Tierra Group conducted hydrologic analyses to determine peak flows due to the 500-year 24‑hour rainfall event and completed the diversion’s civil and hydraulic design for permitting and construction. Challenges included steep topography and limiting rock excavation.

Project Highlights:

  • Heap Leach Pad Design Peer Review
  • Slope Stability Analysis
  • Heap Leach Facility Expansion
  • Permitting Support
  • Geotechnical Investigation
  • Pit Slope Design
  • Geotechnical Modeling
  • Diversion Design
  • Hydrology/Hydraulics

Similar projects

El Gallo Mine

El Gallo is a 3,000 tpd open-pit gold/silver mine located in the foothills of the Sierra Madre Mountain Range in Mexico’s Sinaloa State. Gold is recovered through heap leaching and adsorption/desorption/recovery (ADR). Production commenced at El Gallo with the first gold pour in September…

VIEW PROJECT

Buriticá Tailings Stewardship & Cyanide Speciation

Tierra Group provided Tailings Stewardship Services for Continental Gold’s Buriticá Project in Antioquia, Columbia which included permitting support, Third-Party Review and construction and operations support. Tierra Group oversaw the development of a 2D hydrodynamic model to support the design of…

VIEW PROJECT

Big Ledge Mine

Tierra Group developed a water balance model to track flows into a backfilled pit at the closed Big Ledge Mine Barite Operation near Wells, Nevada. The Model was used to determine pipeline sizing to a remote treatment pond that is…

VIEW PROJECT

Pierina Mine

Barrick Gold Corporation’s Pierina Mine in Ancash Department, Perú began operations in 1998. A progressive reclamation and closure plan began in 2013.  In 2015-16 Tierra Group developed detailed engineering designs for channels, sediment traps, two 45,000 m3 sediment ponds, water…

VIEW PROJECT

Camino Rojo Mine

Heap Leach Procurement & Construction Quality Assurance Tierra Group provided Issued for Construction (IFC) design drawings and specifications for procurement requirements for the expansion of the Camino Rojo HLF. Information required included liner specifications, drainage collection piping, and quantities. Additionally,…

VIEW PROJECT

Oracle Ridge Copper

Tierra Group represented Oracle Ridge Mining as the Qualified Person for portions of the feasibility-level design including the Dry Stack Tailings Storage Facility (TSF) Design, Site-Wide Stormwater Management, Water Supply Pipelines, Haul Road and Access Road Design Improvements, and the…

VIEW PROJECT

New Jersey Mill TSF

Tierra Group completed a siting study to evaluate six potential sites for a paste TSF. Tierra Group prepared civil layouts for each TSF, determining embankment fill volumes, evaluating required diversions for upstream catchment areas, and pipeline corridor layouts. Tierra Group…

VIEW PROJECT

Bolanitos

Tierra Group provided Tailings Stewardship Services including a dam inspection, slope stability analysis review and operational improvements for Endeavour Silver’s Bolanitos tailings storage facility.

VIEW PROJECT

Tajo Crimea Project

Tierra Group evaluated the Tajo Crimea Pit’s geotechnical and hydrogeological characteristics to determine in-pit tailings storage feasibility. The project scope defined geotechnical and hydrogeologic site conditions through field investigations and in-situ pump testing. Tierra Group developed a 3D groundwater model…

VIEW PROJECT

Stibnite Gold Project

The Stibnite project is located in the remote central Idaho Rockies near the town of Yellow Pine.  It is a brownfields gold-antimony project featuring three open pits and an anticipated 22,000 tpd plant throughput, along with challenging terrain and environmental…

VIEW PROJECT

San Albino

Dry Stack Tailings Storage Facility Design Tierra Group supported construction of the San Albino Mine in Nueva Segovia, Nicaragua. Tierra Group designed a dry stack drum filtered-tailings storage facility. A siting study optimized the dry stack location and minimized CAPEX and OPEX.…

VIEW PROJECT

Goldfield Bonanza Project

Lode-Star Gold, Inc., in advance of their proposed mining operations, submited a Physical Separation Facility application with the State of Nevada for their Goldfield Bonanza Project located in Esmeralda County, Nevada. The mine, located in the historic high-grade gold-bearing district of…

VIEW PROJECT