Isabella Pearl

Project Highlights:

  • Heap Leach Pad Design Peer Review
  • Slope Stability Analysis
  • Heap Leach Facility Expansion
  • Permitting Support
  • Geotechnical Investigation
  • Pit Slope Design
  • Geotechnical Modeling
  • Diversion Design
  • Hydrology/Hydraulics

Tierra Group performed a technical peer review of the Isabella Pearl heap leach facility (HLF) owned by Gold Resource Corporation. Isabella Pearl mine is located at the west end of the Santa Fe mining district in the Walker Lane gold belt about 6 miles northeast of Luning, Nevada, in Mineral County. The HLF will have a nominal throughput of 8,000 tons per day over a period of 15 months following of pre-production development and construction. Tierra Group performed the review with the following objectives:

  • Peer review the existing engineering design and drawings to ensure the proposed engineering design is adequate and in conformity with accepted engineering practices;
  • Identify opportunities to “optimize” the design to potentially reduce capital or operating costs; and
  • Identify associated risks (regulatory, financial, construction schedule, etc.) with implementing optimization.

Tierra Group identified a number of optimization opportunities and provided design enhancement recommendations to potentially reduce capital or operation costs.

Expansion Pit Slope Review

Tierra Group conducted an expansion pit slope review that included a technical memorandum of site observations/investigation, a review of past and new data, a basic slope analyses that developed recommendations for slope angles that determined if the Pit Expansion would be stable, and provided suggestions for a slope monitoring program.

HLF Phase 2A Engineering Design Change (EDC)

Tierra Group prepared an EDC to increase the permitted storage height of the existing HLF. A geotechnical field investigation and stability analysis for the Phase 2A and 3 expansion were also completed. Analysis results guided the civil grading and engineering design for each phase.

Crimson Preliminary Pit Slope Design

Tierra Group recommended a field investigation program and geotechnical modeling for the new Crimson Pit near the existing Isabella Pearl Pit. Tierra Group also provided preliminary pit slope design parameters.

Civit Cat Diversion

Tierra Group completed a diversion design to route stormwater around a planned open pit expansion. Tierra Group conducted hydrologic analyses to determine peak flows due to the 500-year 24‑hour rainfall event and completed the diversion’s civil and hydraulic design for permitting and construction. Challenges included steep topography and limiting rock excavation.

Project Highlights:

  • Heap Leach Pad Design Peer Review
  • Slope Stability Analysis
  • Heap Leach Facility Expansion
  • Permitting Support
  • Geotechnical Investigation
  • Pit Slope Design
  • Geotechnical Modeling
  • Diversion Design
  • Hydrology/Hydraulics

Similar projects

Lost Creek Project | USA

Tierra Group is assisting Millcreek Mining and Black Mountain Sand with the preparation of permitting documents for the Lost Creek Project; including a preliminary Stormwater Management Plan, preliminary Groundwater Monitoring Plan, and general permitting exhibits. Tierra Group conducted a site geotechnical…

VIEW PROJECT

Grupo Mexico | La Caridad

Tailings Storage Facility (TSF) AuditTierra Group performed the La Caridad TSF Audit. Tierra Group’s scope of work entailed a site visit, data review, dam safety inspection (DSI), site interviews, and best management practices training for operations personnel.

VIEW PROJECT

Fire Creek Mine

Tierra Group conducted a siting analysis for a new WRSF to support the mine’s future production increase as part of the Preliminary Feasibility Study (PFS). In addition to supporting the PFS, Tierra Group assisted in preparing and submitting several engineering…

VIEW PROJECT

Copperstone Project

Tierra Group International, Ltd. participated as the geotechnical lead engineering firm for the Copperstone Project Pre-Feasibility Study (PFS) in Arizona, U.S.A. Tierra Group was responsible for tailings and waste rock storage, water management and underground geotechnics design and cost estimates…

VIEW PROJECT

Big Ledge Mine

Tierra Group developed a water balance model to track flows into a backfilled pit at the closed Big Ledge Mine Barite Operation near Wells, Nevada. The Model was used to determine pipeline sizing to a remote treatment pond that is…

VIEW PROJECT

Jerritt Canyon Mine

2023 Dam Inspections/Review Tierra Group completed a site visit to inspect three tailings storage facilities (TSFs) and the Evaporation Pond. In addition to the site visit and dam inspections, design and monitoring reports (prepared by others) were reviewed for each…

VIEW PROJECT

El Cubo

Tierra Group provided Tailings Stewardship Services including a dam inspection, slope stability analysis review and operational improvements for Endeavour Silver’s El Cubo tailings storage facility in Guanajuato, Mexico.

VIEW PROJECT

Bunker Hill

Dry Stack Tailings Storage Facility Tierra Group designed a dry stack TSF to store excess tailings from the underground paste backfill. The dry stack TSF was challenging, given the limited land area, steep terrain, seasonal cold weather, and surface water…

VIEW PROJECT

Tennessee Mines

Tierra Group performed Dam Safety Reviews (DSRs) for Nyrstar’s tailings storage facilities (TSFs) located in Tennessee, United States.  Tierra Group served as the Tailings Reviewer to ensure conformity with local regulations, the Nyrstar Tailings Storage Facility (TSF) Standard, and to…

VIEW PROJECT

2020 TSF Annual Dam Inspection

Tierra Group completed an annual dam safety inspection (DSI) to meet both Nevada Division of Water Resources (NDWR) Dam Safety and the client's requirements. The DSI included reviewing monitoring data, a dam and appurtenant structures inspection, and a DSI report.

VIEW PROJECT

Andina Veladero Engineering Review

Tierra Group performed a forensic study to determine the cause for volumetrically non-compliant leakage volumes occurring in the heap leach facilities leak detection system. Tierra Group reviewed the facility design, engineering and construction quality assurance (CQA) information, construction as built…

VIEW PROJECT

Pinos Altos Mine

Tierra Group provided slope stability analysis for Agnico Eagle’s dry stack tailings storage facility containing 330,000 tonnes of tailings.

VIEW PROJECT