Isabella Pearl

Project Highlights:

  • Heap Leach Pad Design Peer Review
  • Slope Stability Analysis
  • Heap Leach Facility Expansion
  • Permitting Support
  • Geotechnical Investigation
  • Pit Slope Design
  • Geotechnical Modeling
  • Diversion Design
  • Hydrology/Hydraulics

Tierra Group performed a technical peer review of the Isabella Pearl heap leach facility (HLF) owned by Gold Resource Corporation. Isabella Pearl mine is located at the west end of the Santa Fe mining district in the Walker Lane gold belt about 6 miles northeast of Luning, Nevada, in Mineral County. The HLF will have a nominal throughput of 8,000 tons per day over a period of 15 months following of pre-production development and construction. Tierra Group performed the review with the following objectives:

  • Peer review the existing engineering design and drawings to ensure the proposed engineering design is adequate and in conformity with accepted engineering practices;
  • Identify opportunities to “optimize” the design to potentially reduce capital or operating costs; and
  • Identify associated risks (regulatory, financial, construction schedule, etc.) with implementing optimization.

Tierra Group identified a number of optimization opportunities and provided design enhancement recommendations to potentially reduce capital or operation costs.

Expansion Pit Slope Review

Tierra Group conducted an expansion pit slope review that included a technical memorandum of site observations/investigation, a review of past and new data, a basic slope analyses that developed recommendations for slope angles that determined if the Pit Expansion would be stable, and provided suggestions for a slope monitoring program.

HLF Phase 2A Engineering Design Change (EDC)

Tierra Group prepared an EDC to increase the permitted storage height of the existing HLF. A geotechnical field investigation and stability analysis for the Phase 2A and 3 expansion were also completed. Analysis results guided the civil grading and engineering design for each phase.

Crimson Preliminary Pit Slope Design

Tierra Group recommended a field investigation program and geotechnical modeling for the new Crimson Pit near the existing Isabella Pearl Pit. Tierra Group also provided preliminary pit slope design parameters.

Civit Cat Diversion

Tierra Group completed a diversion design to route stormwater around a planned open pit expansion. Tierra Group conducted hydrologic analyses to determine peak flows due to the 500-year 24‑hour rainfall event and completed the diversion’s civil and hydraulic design for permitting and construction. Challenges included steep topography and limiting rock excavation.

Project Highlights:

  • Heap Leach Pad Design Peer Review
  • Slope Stability Analysis
  • Heap Leach Facility Expansion
  • Permitting Support
  • Geotechnical Investigation
  • Pit Slope Design
  • Geotechnical Modeling
  • Diversion Design
  • Hydrology/Hydraulics

Similar projects

Bunker Hill

Dry Stack Tailings Storage Facility Tierra Group designed a dry stack TSF to store excess tailings from the underground paste backfill. The dry stack TSF was challenging, given the limited land area, steep terrain, seasonal cold weather, and surface water…

VIEW PROJECT

Los Gatos Project

TSF Design and CQA Tierra Group provided detailed Stage 1 and 2 Tailings Storage Facility design, conducted a process plant geotechnical foundation investigation, and provided Construction Quality Assurance for Sunshine Silver Mining's Los Gatos Project in Chihuahua, Mexico. Tierra Group then…

VIEW PROJECT

Buriticá Tailings Stewardship & Cyanide Speciation

Tierra Group provided Tailings Stewardship Services for Continental Gold’s Buriticá Project in Antioquia, Columbia which included permitting support, Third-Party Review and construction and operations support. Tierra Group oversaw the development of a 2D hydrodynamic model to support the design of…

VIEW PROJECT

Pit Slope Design | County Line Project

Tierra Group conducted a geotechnical investigation program to provide data for pit slope design. Tierra Group provided field support through oriented core logging, pit wall mapping, selected samples for laboratory testing, and provided pit slope design recommendations for safe open…

VIEW PROJECT

NioCorp’s Elk Creek | Tailings Storage Facility (TSF) Feasibility Study

Tierra Group advanced the TSF design to a Feasibility Level according to the Canadian National Instrument NI 43-101 and the U.S. Security and Exchange Commission’s Subpart SK-1300 regulation. Tierra Group’s scope of work included a geotechnical investigation, engineering analysis, and TSF…

VIEW PROJECT

San Andrés Mine

Previous to Tierra Group, our Team performed a geotechnical forensics assessment, which determined that spent ore from an on-off leach pad operation had liquefied causing a debris flow, which threatened inundating a major river basin. A preventative detention buttress was…

VIEW PROJECT

Equity Silver ITRB

Tierra Group's Matt Fuller, LEG, P.Geo. serves as one of three ITRB technical experts providing technical assurance of the Engineer of Record’s design and monitoring compliance with BC regulations, the Newmont Corporate Tailings Standard, and industry best practices.

VIEW PROJECT

El Aguila

Dry Stack Tailings Options Analysis Tierra Group performed an independent TSF expansion engineering design peer review. The review resulted in cost savings ($650,000) without compromising the facility's design integrity over the original design. Tierra Group also provided full-time CQA. Tierra…

VIEW PROJECT

Big Ledge Mine

Tierra Group developed a water balance model to track flows into a backfilled pit at the closed Big Ledge Mine Barite Operation near Wells, Nevada. The Model was used to determine pipeline sizing to a remote treatment pond that is…

VIEW PROJECT

Palmarejo Mine

Tierra Group performed an initial site visit to Coeur Mining’s Palmarejo Mine to conduct dam safety inspections of the tailings storage facility, environmental control dam, water diversion dam, and water diversion channel. Prior to the site visit, Tierra Group reviewed…

VIEW PROJECT

Ray Mine

Tierra Group is implementing a corporate Tailings Stewardship Strategy (TSS) at all of ASARCO Grupo Mexico’s mines in Arizona, USA (Hayden, Mission and Ray mines). Tierra Group conducted a site visit to each site to perform dam safety inspections, interview…

VIEW PROJECT

La Libertad Mine

Tierra Group engineers designed La Esperanza TSF, a 2.1-km long, 35-m high, earthfill tailings dam with an HDPE lined impoundment footprint of 840,000 m2. Tierra Group designed and provided Construction Quality Assurance (CQA) for all subsequent downstream dam stages. Stage…

VIEW PROJECT