Esmeralda Mill

Project Highlights:

  • Tailings Dams
  • Geotechnical
  • Water Management
  • Permitting Support
  • Planning
  • Closure/Reclamation
  • Waste Rock Dumps
  • Construction Support

Tierra Group was contracted by Waterton Global Mining Company to prepare the FPCP for TSF No.1 at the Esmeralda Mine. TSF No.1 covered approximately 100 acres, included a rockfill embankment with a maximum height approximately 60 feet, and stored gold tailings. Work included summarizing tailings characterization data, completing the civil design for tailings regrading and closure soil cover placement, estimation of long-term soil loss using RUSLE, design and evaluation of a closure cover, design of a closure spillway capable of safely conveying the peak flow due to the 100-year 24-hour storm event, development of a surface water management plan, development of post-closure water management and monitoring plans, and writing the FPCP for submittal to Nevada Division of Environmental Protection (NDEP).

Project Highlights:

  • Tailings Dams
  • Geotechnical
  • Water Management
  • Permitting Support
  • Planning
  • Closure/Reclamation
  • Waste Rock Dumps
  • Construction Support

Similar projects

Pirquitas Tailings Review

Tierra Group prepared a civil engineering design for SSR Mining’s Mina Pirquitas in Jujuy Province, Argentina and developed current and future water-mass balance through hydrological/hydraulics calculations and modeling. Tierra Group developed the ultimate tailings surface, deposition plan, spillway relocation analysis,…

VIEW PROJECT

Midas Mine

The Midas Mine is located in northern Nevada, and is owned and operated by Hecla Mining Company.  The mine is an underground mine with an operating mill. The mine’s existing tailings facilities are nearing their end of operating life and…

VIEW PROJECT

Stillwater Mine

East Boulder Tailings Independent Review Panel (2018-present) Tierra Group reviewed a TSF design to support an NI 43-101 compliant Feasibility Study. The TSF design incorporated a paste tailings disposal method in an environmentally sensitive fisheries habitat. Tierra Group sits on the Independent…

VIEW PROJECT

Pierina Mine

Barrick Gold Corporation’s Pierina Mine in Ancash Department, Perú began operations in 1998. A progressive reclamation and closure plan began in 2013.  In 2015-16 Tierra Group developed detailed engineering designs for channels, sediment traps, two 45,000 m3 sediment ponds, water…

VIEW PROJECT

2020 TSF Annual Dam Inspection

Tierra Group completed an annual dam safety inspection (DSI) to meet both Nevada Division of Water Resources (NDWR) Dam Safety and the client's requirements. The DSI included reviewing monitoring data, a dam and appurtenant structures inspection, and a DSI report.

VIEW PROJECT

Dam Assessment

Tierra Group performed a site visit and visual inspection of a dam to assess its overall condition and provide the Owner recommendations for continued maintenance, monitoring, and improvements. The assessment was a follow-up to previous work completed by Tierra Group…

VIEW PROJECT

Pitarrilla Mine

Tierra Group participated as a member of a multi-disciplinary project team to develop a Definitive Feasibility study for a 16,000 tpd silver mine in Durango, Mexico. Tierra Group's responsibilities included designing a 112 Mt tailings storage facility, developing a site-wide…

VIEW PROJECT

Lost Creek Project | USA

Tierra Group is assisting Millcreek Mining and Black Mountain Sand with the preparation of permitting documents for the Lost Creek Project; including a preliminary Stormwater Management Plan, preliminary Groundwater Monitoring Plan, and general permitting exhibits. Tierra Group conducted a site geotechnical…

VIEW PROJECT

Morelos Mine

Tierra Group designed and implemented a stability and safety monitoring plan for Torex Gold’s Morelos Mine dry stack tailings storage facility (TSF). The monitoring plan includes installing inclinometers and vibrating wire piezometers, and training operations staff to download instrumentation readings.…

VIEW PROJECT

Brushy Creek

Tierra Group provided a raise design for Doe Run's Brushy Creek tailings embankment, a facility first commissioned in 1973. Cone penetration testing, liquefaction analysis, seepage modeling, and slope stability modeling were performed for the embankment. Hydrology, spillway design, and impoundment layout…

VIEW PROJECT

Peñasquito

Tierra Group was selected to assist Goldcorp with global Tailings Stewardship Strategy (TSS) implementation at all of Goldcorp’s active tailings sites in Latin America (Mexico, Argentina, and Guatemala). Tierra Group worked in conjunction with Goldcorp and another global engineering consulting…

VIEW PROJECT

Tailings Review & Assurance Audit | Montana

Tailings Management Assurance Review Tierra Group served as the Lead Auditor and conducted MARs for the TSFs at this confidential project. Tierra Group reviewed all available facility documentation, including OMS Manuals, EAPs, design reports, As-Built Reports, annual inspection reports, and other…

VIEW PROJECT