Andina Veladero Engineering Review

Project Highlights:

  • Third-Party Review
  • Construction Quality Assurance
  • Cold Climate
  • High Altitude
  • Gold

Tierra Group performed a forensic study to determine the cause for volumetrically non-compliant leakage volumes occurring in the heap leach facilities leak detection system. Tierra Group reviewed the facility design, engineering and construction quality assurance (CQA) information, construction as built drawings, and summarized findings in a technical memorandum.

Project Highlights:

  • Third-Party Review
  • Construction Quality Assurance
  • Cold Climate
  • High Altitude
  • Gold

Similar projects

La Libertad Mine

Tierra Group engineers designed La Esperanza TSF, a 2.1-km long, 35-m high, earthfill tailings dam with an HDPE lined impoundment footprint of 840,000 m2. Tierra Group  designed and provided Construction Quality Assurance (CQA) for all subsequent downstream dam stages. Stage…

VIEW PROJECT

Camino Rojo Heap Leach Design

Tierra Group provided a heap leach facility detailed design (for construction), procurement, CQA and project management for the Camino Rojo Mine in Zacatecas, Mexico.

VIEW PROJECT

Pierina Mine

Barrick Gold Corporation’s Pierina Mine in Ancash Department, Perú began operations in 1998. A progressive reclamation and closure plan began in 2013.  In 2015-16 Tierra Group developed detailed engineering designs for channels, sediment traps, two 45,000 m3 sediment ponds, water…

VIEW PROJECT

Mt. Todd Dam Assessment

Tierra Group conducted an Independent Technical review of Vista Gold Corp’s Mt. Todd Tailings Storage Facility Expansion in Northern Territory, Australia.

VIEW PROJECT

Caeté Complex

Tierra Group developed a site-wide water management plan, and performed a liquefaction potential study following the Samarco tailings dam failure in Minas Gerais, Brazil. A tailings storage facility water balance was developed to optimize water usage and minimize risks at…

VIEW PROJECT

El Aguila

Tierra Group performed a 3rd party engineering design peer review of a tailings storage facility expansion design. The review resulted in the owner realizing $650,000 in cost savings without compromising the facility's design integrity over the original design. Tierra Group also…

VIEW PROJECT

Tonopah Flats | Tailings Storage Facility

Tierra Group assisted with developing tailings disposal alternatives.

VIEW PROJECT

Midas Gold Project

Midas Gold’s project is located in the remote central Idaho Rockies near the town of Yellow Pine.  It is a brownfields gold-antimony project featuring three open pits and an anticipated 22,000 tpd plant throughput, along with challenging terrain and environmental…

VIEW PROJECT

Andina Veladero Engineering Review

Tierra Group performed a forensic study to determine the cause for volumetrically non-compliant leakage volumes occurring in the heap leach facilities leak detection system. Tierra Group reviewed the facility design, engineering and construction quality assurance (CQA) information, construction as built…

VIEW PROJECT

NioCorp’s Elk Creek | Tailings Storage Facility (TSF) Feasibility Study

Tierra Group advanced the TSF design to a Feasibility Level according to the Canadian National Instrument NI 43-101 and the U.S. Security and Exchange Commission’s Subpart SK-1300 regulation. Tierra Group’s scope of work included a geotechnical investigation, engineering analysis, and TSF…

VIEW PROJECT

Pinos Altos Mine

Tierra Group provided slope stability analysis for Agnico Eagle’s dry stack tailings storage facility containing 330,000 tonnes of tailings.

VIEW PROJECT

Dam Assessment

Tierra Group performed a site visit and visual inspection of a dam to assess its overall condition and provide the Owner recommendations for continued maintenance, monitoring, and improvements. The assessment was a follow-up to previous work completed by Tierra Group…

VIEW PROJECT