Tailings Review & Assurance Audit | Montana

Project Highlights:

  • Independent Engineering Review
  • Tailings Storage Facilities
  • Tailings Assurance Audit

Tailings Management Assurance Review

Tierra Group served as the Lead Auditor and conducted MARs for the TSFs at this confidential project. Tierra Group reviewed all available facility documentation, including OMS Manuals, EAPs, design reports, As-Built Reports, annual inspection reports, and other relevant documentation in determining each site’s compliance with the Company’s Tailings and Heap Leach Management Standard.

Independent Engineer's Review

Tierra Group personnel served as the Audit Lead to review tailings management procedures and compared them to standards outlined in the Company’s Corporate Tailings and Heap Leach Management Standard.

Tailings Assurance Audit

Tierra Group completed a Tailings Assurance Audit (TAA) for Tailings Storage Facility 2 (TSF2). The TAA was completed to ensure the TSF and site operations complied with the Company’s Tailings Management Standard, which closely mirrors Global Industry Standard on Tailings Management (GISTM) requirements. 

Project Highlights:

  • Independent Engineering Review
  • Tailings Storage Facilities
  • Tailings Assurance Audit

Similar projects

American Gypsum

American Gypsum Pit Planning and Support Tierra Group began working at American Gypsum’s Eagle-Gypsum mine located in Gypsum, Colorado in 2014 evaluating haul road improvements. A trade-off study provided a tool for American Gypsum to evaluate safety improvements including alternative haul road…

VIEW PROJECT

Çöpler Tailings Storage Facility and Heap Leach Facility Technical Review

Tierra Group has a history of annually providing third-party technical reviews for the tailings storage facility and heap leach facility at Anagold's Çöpler Gold Mine in Middle Anatolia, Turkey. Additionally, Tierra Group currently performs independent technical reviews for the rockfill…

VIEW PROJECT

La India Mine

GoldSim Training Tierra Group provided GoldSim training to the Agnico Team and updated the heap leach water balance. Phase 2 & 3 Heap Leach Pad Design and Construction Quality Assurance Tierra Group provided engineering design services for the Phase 2 and 3…

VIEW PROJECT

Cove Project RIB Geotechnical Investigation

Tierra Group supported proposed Rapid Infiltration Basins Geotechnical Investigation at Au-reka Gold Corporation’s Cove Project in Nevada. Investigation included borehole drilling, test pits, infiltration testing and permeability testing.

VIEW PROJECT

Masbate Mine

Tierra Group performed a study of Masbate’s 12-Mt tailings storage facility. Services provided included a forensic study to determine the cause of seepage through an abutment and performed an independent safety audit of tailings management practices. A risk analysis was performed…

VIEW PROJECT

San Bartolome Mine | NI 43-101 Tailings Technical Review & Report

Tierra Group performed an Independent Tailings Technical Review to support the San Bartolomé Mine Prefeasibility Study (PFS) NI 43-101 Technical Report (TR). SRK Consulting Inc. (SRK) is the primary TR author. Tierra Group will provided a Qualified Person (QP) to oversee…

VIEW PROJECT

Sterling Mine

Sterling Mine is an underground gold mine in southern Nevada which recovers gold through heap leaching and a carbon adsorption-desorption-recovery (ADR) plant. Tierra Group team members have a long history at Sterling, starting with heap leach pad final permanent closure…

VIEW PROJECT

Hermosa Project

Tierra Group provided a Third-Party review of the Hermosa Project Tailings Storage Facility Design and Construction stages 1 & 2 in Patagonia, Arizona

VIEW PROJECT

Pierina Mine

Barrick Gold Corporation’s Pierina Mine in Ancash Department, Perú began operations in 1998. A progressive reclamation and closure plan began in 2013.  In 2015-16 Tierra Group developed detailed engineering designs for channels, sediment traps, two 45,000 m3 sediment ponds, water…

VIEW PROJECT

Douglas County Public Works

Tierra Group updated the County’s Standard Operating Procedures (SOPs) for Municipal Operations to maintain the County’s compliance with the requirements for stormwater discharges from the County’s municipal separate storm sewer system (MS4) under the Colorado Discharge Permit System (CDPS). Tierra…

VIEW PROJECT

Esmeralda Mill

Tierra Group was contracted by Waterton Global Mining Company to prepare the FPCP for TSF No.1 at the Esmeralda Mine. TSF No.1 covered approximately 100 acres, included a rockfill embankment with a maximum height approximately 60 feet, and stored gold tailings. Work…

VIEW PROJECT

San Francisco Mine

Tierra Group conducted geo-electrical testing to locate leaks present in the geomembrane liners underlying a Solution Conveyance Canal, Sumps 1 and 2, and the Intermediate Pond at Timmins Gold Corp’s San Francisco Mine in Sonora, Mexico. Leak detection testing procedures…

VIEW PROJECT