Bolanitos

Project Highlights:

  • Tailings Stewardship Services

Tierra Group provided Tailings Stewardship Services including a dam inspection, slope stability analysis review and operational improvements for Endeavour Silver’s Bolanitos tailings storage facility.

Project Highlights:

  • Tailings Stewardship Services

Similar projects

Gediktepe Peer Review

Tierra Group provided technical direction and review of the Gediktepe Heap Leach Facility (HLF), ponds, and waste rock dump facility designs. Tierra Group will also provide CQA review during HLF construction.

VIEW PROJECT

Cove Project RIB Geotechnical Investigation

Tierra Group supported proposed Rapid Infiltration Basins Geotechnical Investigation at Au-reka Gold Corporation’s Cove Project in Nevada. Investigation included borehole drilling, test pits, infiltration testing and permeability testing.

VIEW PROJECT

Hermosa Project

Tierra Group provided a Third-Party review of the Hermosa Project Tailings Storage Facility Design and Construction stages 1 & 2 in Patagonia, Arizona

VIEW PROJECT

Dona Lake DSR

Serving on Newmont Goldcorp’s Tailings Independent Review Board, Tierra Group provided an Independent Dam Safety Review for the Dona Lake Mine tailings storage facility in Pickle Lake, Ontario, Canada.

VIEW PROJECT

North Mara Mine | Tailings Assurance Audit

Tierra Group completed a TAA for the North Mara Tailings Storage Facility (TSF). The TAA was completed to ensure the TSF and site operations complied with Barrick’s Tailings Management Standard, which closely mirrors the Global Industry Standard on Tailings Management (GISTM)…

VIEW PROJECT

Bolivar Mine

The Bolivar mine is a 3,000 tonne per day underground mining operation in Chihuahua, Mexico producing copper, zinc, silver, and gold. Space constraints in mountainous terrain require dewatering tailings to reduce required area for tailings storage. Tierra Group is assisting…

VIEW PROJECT

El Cubo

Tierra Group provided Tailings Stewardship Services including a dam inspection, slope stability analysis review and operational improvements for Endeavour Silver’s El Cubo tailings storage facility in Guanajuato, Mexico.

VIEW PROJECT

San Albino Dry Stack Tailings Storage Facility Design

Tierra Group supported construction of the San Albino Mine in Nueva Segovia, Nicaragua. Tierra Group designed a dry stack drum filtered-tailings storage facility. A siting study optimized the dry stack location and minimized CAPEX and OPEX. Tierra Group developed a site-wide water…

VIEW PROJECT

Don Mario Gold Mine

Don Mario Mine is an open pit gold/copper mine located in the Chiquitos Province, Santa Cruz, Bolivia that has been operating since 2002 and currently produces 2700 tpd mill throughput. Conventional tailings are transported and deposited in a high-density polyethylene lined geomembrane valley…

VIEW PROJECT

Myra Falls

Tierra Group provides Tailings Stewardship Services for Nyrstar's Myra Falls Mine Tailings Storage Facility. Tierra Group performed a 5-year Dam Safety Review consistent with the Canadian Dam Association protocols, site training and in depth inspections of management practices and facilities…

VIEW PROJECT

Newcrest Red Chris Tailings Stewardship

Tierra Group provided Tailings Stewardship Services for TSFs and water dams at the Cadia, Terfer, and Red Chris properties. Responsibilities included data/report review; identifying and assisting the client with managing risks, liabilities, controls, and reporting; evaluating progress towards GISTM compliance;…

VIEW PROJECT

Palmarejo Mine

Tierra Group performed an initial site visit to Coeur Mining’s Palmarejo Mine to conduct dam safety inspections of the tailings storage facility, environmental control dam, water diversion dam, and water diversion channel. Prior to the site visit, Tierra Group reviewed…

VIEW PROJECT