Tierra Group provided Tailings Stewardship Services including a dam inspection, slope stability analysis review and operational improvements for Endeavour Silver’s Bolanitos tailings storage facility.
Tierra Group performed an independent technical peer review of the Boleo Mine’s operating tailings storage facility design. In doing so Tierra Group identified several design modifications that when implemented for future stages will reduce sustaining capital cost expenditures by several…
Tierra Group performed an independent engineering design review of a Cemented Tailings Facility (CTF) and multiple processes and freshwater ponds. Tailings will be mixed with cement at the paste plant and deposited in the CTF along with underground mine development…
Tierra Group International, Ltd. participated as the geotechnical lead engineering firm for the Copperstone Project Pre-Feasibility Study (PFS) in Arizona, U.S.A. Tierra Group was responsible for tailings and waste rock storage, water management and underground geotechnics design and cost estimates…
Tierra Group developed a site-wide water management plan, and performed a liquefaction potential study following the Samarco tailings dam failure in Minas Gerais, Brazil. A tailings storage facility water balance was developed to optimize water usage and minimize risks at…
Tierra Group conducted geo-electrical testing to locate leaks present in the geomembrane liners underlying a Solution Conveyance Canal, Sumps 1 and 2, and the Intermediate Pond at Timmins Gold Corp’s San Francisco Mine in Sonora, Mexico. Leak detection testing procedures…
Tierra Group completed an annual dam safety inspection (DSI) to meet both Nevada Division of Water Resources (NDWR) Dam Safety and the client's requirements. The DSI included reviewing monitoring data, a dam and appurtenant structures inspection, and a DSI report.
Tierra Group evaluated the Tajo Crimea Pit’s geotechnical and hydrogeological characteristics to determine in-pit tailings storage feasibility. The project scope defined geotechnical and hydrogeologic site conditions through field investigations and in-situ pump testing. Tierra Group developed a 3D groundwater model…
Tierra Group conducted an update of the Mexican Hat Project’s Preliminary Economic Assessment. Tierra Group’s update included the heap leach facility design and preliminary stacking plan, waste rock storage pad, and crushed rock storage pad design.
Tierra Group performed a Dam Safety Review (DSR) including geotechnical investigations and seepage and slope stability analyses for a 20-m high TSF at this 300‑tpd underground polymetallic mine. The audit was prepared following the Mt. Polley tailings dam failure in…
Tierra Group designed the Bunker Hill dry stack TSF. The TSF design was challenging given the limited land area, steep terrain, seasonal cold weather, and surface water management. Tierra Group’s scope of work included siting the facilities, geotechnical investigations, civil…
Engineer of Record Barrick’s Goldstrike Mine processes 30,000 tons of gold ore per day from its combined open-pit/underground operations located in the historic Carlin Trend in Nevada, U.S.A. Goldstrike’s tailings are stored in the North Block Tailings Disposal Facility (NBTDF).…
Tierra Group provided technical direction and review of the Gediktepe Heap Leach Facility (HLF), ponds, and waste rock dump facility designs. Tierra Group will also provide CQA review during HLF construction.