Masbate Mine

Project Highlights:

  • Forensics Analysis
  • Due Diligence
  • Mine Plan Optimization
  • Water Management
  • Water Treatment

Tierra Group performed a study of Masbate’s 12-Mt tailings storage facility. Services provided included a forensic study to determine the cause of seepage through an abutment and performed an independent safety audit of tailings management practices. A risk analysis was performed and water management optimization recommendations were made. Tierra Group and its sub-consultants then designed and commissioned a 15,000-m3/d supernatant water treatment plant. The water treatment plant was commissioned in early 2015 and has run continuously at 90 to 95% efficiency, greatly improving the mine’s site-wide water balance.

Project Highlights:

  • Forensics Analysis
  • Due Diligence
  • Mine Plan Optimization
  • Water Management
  • Water Treatment

Similar projects

Andina Veladero Engineering Review

Tierra Group performed a forensic study to determine the cause for volumetrically non-compliant leakage volumes occurring in the heap leach facilities leak detection system. Tierra Group reviewed the facility design, engineering and construction quality assurance (CQA) information, construction as built…

VIEW PROJECT

Boleo Mine

Tierra Group performed an independent technical peer review of the Boleo Mine’s operating tailings storage facility design. In doing so Tierra Group identified several design modifications that when implemented for future stages will reduce sustaining capital cost expenditures by several…

VIEW PROJECT

Mexican Hat PEA Update

Tierra Group conducted an update of the Mexican Hat Project’s Preliminary Economic Assessment. Tierra Group’s update included the heap leach facility design and preliminary stacking plan, waste rock storage pad, and crushed rock storage pad design.

VIEW PROJECT

Sepon Mine CQA

Tierra Group performed Resident Engineering and Construction Quality Control/Assurance during a pilot Heap Leach Facility construction, and Life of Mine Heap Leach and Tailings Sorage Facility siting, design, and tailings management at Lane Xang Minerals' Sepon Mine in Laos.

VIEW PROJECT

Myra Falls

Tierra Group provides Tailings Stewardship Services for Nyrstar's Myra Falls Mine Tailings Storage Facility. Tierra Group performed a 5-year Dam Safety Review consistent with the Canadian Dam Association protocols, site training and in depth inspections of management practices and facilities…

VIEW PROJECT

Santa Pancha Mine

Tierra Group provided a desktop and field review of B2Gold’s Santa Pancha Mine hydrogeology. The review identified data gaps in site data and provided recommendations for improve an existing site hydrogeology model and improve underground water management. The hydrogeologic model…

VIEW PROJECT

Caeté Complex

Tierra Group developed a site-wide water management plan, and performed a liquefaction potential study following the Samarco tailings dam failure in Minas Gerais, Brazil. A tailings storage facility water balance was developed to optimize water usage and minimize risks at…

VIEW PROJECT

Hermosa Project

Tierra Group provided a Third-Party review of the Hermosa Project Tailings Storage Facility Design and Construction stages 1 & 2 in Patagonia, Arizona

VIEW PROJECT

El Aguila

Tierra Group performed a 3rd party engineering design peer review of a tailings storage facility expansion design. The review resulted in the owner realizing $650,000 in cost savings without compromising the facility's design integrity over the original design. Tierra Group also…

VIEW PROJECT

Newcrest Red Chris Tailings Stewardship

Tierra Group provided Tailings Stewardship Services for TSFs and water dams at the Cadia, Terfer, and Red Chris properties. Responsibilities included data/report review; identifying and assisting the client with managing risks, liabilities, controls, and reporting; evaluating progress towards GISTM compliance;…

VIEW PROJECT

North Mara Mine | Tailings Assurance Audit

Tierra Group completed a TAA for the North Mara Tailings Storage Facility (TSF). The TAA was completed to ensure the TSF and site operations complied with Barrick’s Tailings Management Standard, which closely mirrors the Global Industry Standard on Tailings Management (GISTM)…

VIEW PROJECT

Pinos Altos Mine

Tierra Group provided slope stability analysis for Agnico Eagle’s dry stack tailings storage facility containing 330,000 tonnes of tailings.

VIEW PROJECT