La Libertad Mine

Project Highlights:

  • Geologic Hazard Assessment
  • Detailed Design for Construction
  • Earthfill Conventional TSF
  • Environmental Permitting
  • Feasibility Design
  • CQA
  • As-Built Drawings and Report
  • Operations Plans
  • Dam Monitoring
  • Tailings Storage Facility
  • Geotechnical Investigation
  • In-Pit Tailings Disposal
  • Operations, Maintenance, and Surveillance Manual

Tierra Group engineers designed La Esperanza TSF, a 2.1-km long, 35-m high, earthfill tailings dam with an HDPE lined impoundment footprint of 840,000 m2. Tierra Group  designed and provided Construction Quality Assurance (CQA) for all subsequent downstream dam stages. Stage 6 and 7 dam crest raise designs incorporated mechanically stabilized earth (MSE) methods to maintain the facility within property boundaries, and reduce construction costs. Tierra Group also developed the detailed closure design for the Esperanza TSF. 

Tierra Group serves as the Engineer of Record (EoR) for the Esperanza TSF. As the EoR, Tierra Group conducted TSF dam breach and downstream inundation analyses, developed detailed TSF water balance, reviewed monthly monitoring data, conducted annual TSF inspections, and prepared an annual monitoring report to document TSF performance and dam safety.

Crimea In-Pit Tailings Storage Facility (TSF)

Tierra Group developed the Crimea In-Pit TSF Operations, Maintenance, and Surveillance (OMS) Manual and Emergency Action Plan (EAP). for the Crimea In-Pit TSF.

La Esperanza Tailings Storage Facility (TSF)

Tierra Group updated the La Esperanza TSF Operations, Maintenance, and Surveillance (OMS) Manual and Emergency Action Plan (EAP). for the La Esperanza TSF.

Crimea In-Pit Tailings Storage Facility (TSF) Phase 2 Geotechnical Investigation

Tierra Group completed a geotechnical field investigation to support the Crimea TSF Phase 2 design. Field investigation included exploratory borings, trenches, and laboratory testing on dam foundation materials and proposed borrow sources.

Project Highlights:

  • Geologic Hazard Assessment
  • Detailed Design for Construction
  • Earthfill Conventional TSF
  • Environmental Permitting
  • Feasibility Design
  • CQA
  • As-Built Drawings and Report
  • Operations Plans
  • Dam Monitoring
  • Tailings Storage Facility
  • Geotechnical Investigation
  • In-Pit Tailings Disposal
  • Operations, Maintenance, and Surveillance Manual

Similar projects

Guanacevi

Tierra Group provided Tailings Stewardship Services, including a dam inspection, slope stability review and operational improvements. The Guanacevi tailings storage facility, located in Durango, Mexico, consists of dry-stack (Press filtered) tailings placed atop a conventional (slurry) tailings storage facility.

VIEW PROJECT

Amulsar Gold Project

Tierra Group completed a technical review of the heap leach pad for the Amulsar Mine property owned by Lydian Armenia located near the town of Jermuk to the southeast of Armenia. The heap leach pad consists of four phases with…

VIEW PROJECT

Camino Rojo Heap Leach Design

Tierra Group provided a heap leach facility detailed design (for construction), procurement, CQA and project management for the Camino Rojo Mine in Zacatecas, Mexico.

VIEW PROJECT

Esmeralda Mill

Tierra Group was contracted by Waterton Global Mining Company to prepare the FPCP for TSF No.1 at the Esmeralda Mine. TSF No.1 covered approximately 100 acres, included a rockfill embankment with a maximum height approximately 60 feet, and stored gold tailings. Work…

VIEW PROJECT

Bunker Hill

Dry Stack Tailings Storage Facility Tierra Group designed a dry stack TSF to store excess tailings from the underground paste backfill. The dry stack TSF was challenging, given the limited land area, steep terrain, seasonal cold weather, and surface water…

VIEW PROJECT

Topia Mine

Topia Mine Phases 1-3Tierra Group supervised the first 3 phases of Geologic Mapping and Instrumentation Installation and developed a Mechanically Stabilized Earth Wall Design at Great Panther Silver’s Topia Mine in Durango, Mexico.

VIEW PROJECT

Terronera Project

Hydrogeologic Characterization Tierra Group provided hydrogeological support for data characterization and developed a conceptual and groundwater model to evaluate mine water inflows and the associated groundwater drawdown due to mine dewatering activities. Water Management Technical Review Tierra Group provided a…

VIEW PROJECT

Pirquitas Tailings Review

Tierra Group prepared a civil engineering design for SSR Mining’s Mina Pirquitas in Jujuy Province, Argentina and developed current and future water-mass balance through hydrological/hydraulics calculations and modeling. Tierra Group developed the ultimate tailings surface, deposition plan, spillway relocation analysis,…

VIEW PROJECT

Buriticá Tailings Stewardship & Cyanide Speciation

Tierra Group provided Tailings Stewardship Services for Continental Gold’s Buriticá Project in Antioquia, Columbia which included permitting support, Third-Party Review and construction and operations support. Tierra Group oversaw the development of a 2D hydrodynamic model to support the design of…

VIEW PROJECT

Don Mario Gold Mine

Don Mario Mine is an open pit gold/copper mine located in the Chiquitos Province, Santa Cruz, Bolivia that has been operating since 2002 and currently produces 2700 tpd mill throughput. Conventional tailings are transported and deposited in a high-density polyethylene lined geomembrane valley…

VIEW PROJECT

Newcrest Red Chris Tailings Stewardship

Tierra Group provided Tailings Stewardship Services for TSFs and water dams at the Cadia, Terfer, and Red Chris properties. Responsibilities included data/report review; identifying and assisting the client with managing risks, liabilities, controls, and reporting; evaluating progress towards GISTM compliance;…

VIEW PROJECT

Dona Lake DSR

Serving on Newmont Goldcorp’s Tailings Independent Review Board, Tierra Group provided an Independent Dam Safety Review for the Dona Lake Mine tailings storage facility in Pickle Lake, Ontario, Canada.

VIEW PROJECT