Mascota Mine

Project Highlights:

  • Heap Leach Design
  • Civil Design
  • Geotechnical Investigation
  • Water Balance
  • Buttress Design
  • Construction Quality Assurance
Creston Mascota Mine is located in Chihuahua, Mexico and is owned and operated by Agnico Eagle Mexico. Tierra Group designed the Phase 4 heap leach pad, buttress, which included geotechnical investigations, slope stability analyses and a water balance for Agnico Eagle’s Mascota Mine 5,000 tpd heap leach pad (combined with Pinos Altos ore) in Chihuahua, Mexico. In addition, Tierra Group provided Construction Quality Assurance (CQA) services for phase 3 and phase 4 pad construction.

Phase 5 Heap Leach Pad is an expansion of Phase 4 with a proposed capacity of 2 to 3 million tons (Mt) of crushed ore. The project includes development of construction drawings and technical specifications to be used for the construction of the facility. The design includes slope stability analyses, seepage analyses, water balance to verify the size of existing ponds, and stormwater management to design diversion channels.

Tierra Group will also provide Construction Quality Assurance (CQA) services for the construction of the heap expansion, including construction observation, clay placement and compaction, and liner installation.

Project Highlights:

  • Heap Leach Design
  • Civil Design
  • Geotechnical Investigation
  • Water Balance
  • Buttress Design
  • Construction Quality Assurance

Similar projects

Pan American Shahuindo Engineering Design

Tierra Group performed a detailed engineering design for a 4km access road and diversion channel, and the feasibility design for water diversion structures (including electrical and mechanical layout for a pump station). Tierra Group also performed a geotechnical investigation and updated…

VIEW PROJECT

El Cubo

Tierra Group provided Tailings Stewardship Services including a dam inspection, slope stability analysis review and operational improvements for Endeavour Silver’s El Cubo tailings storage facility in Guanajuato, Mexico.

VIEW PROJECT

El Gallo Mine

El Gallo is a 3,000 tpd open-pit gold/silver mine located in the foothills of the Sierra Madre Mountain Range in Mexico’s Sinaloa State. Gold is recovered through heap leaching and adsorption/desorption/recovery (ADR). Production commenced at El Gallo with the first gold pour in September…

VIEW PROJECT

Yauricocha Mine

The Yauricocha Mine is a polymetallic (copper, lead, zinc) underground mine located in Yauyos Province, Lima, Peru. Tailings are deposited in the Yauricocha Tailings Storage Facility (TSF) located 3km from the process plant. Tierra Group was engaged in 2015 to…

VIEW PROJECT

Morro do Ipe Due Diligence

Tierra Group served on an Independent Engineering Team performing a tailings management and operations Due Diligence Technical Review at the Morro do Ipe iron ore mine in Minas Gerais, Brazil.

VIEW PROJECT

Tajo Crimea Project

Tierra Group evaluated geotechnical and hydrogeological characteristics of Tajo Crimea Pit to determine in-pit tailings storage feasibility. The project scope defined geotechnical and hydrogeologic site conditions through field investigations, and in-situ pump testing. A 3D groundwater model was developed to…

VIEW PROJECT

Karouni Mine

Tierra Group reviewed and provided pit slope recommendations and conducted hydrological assessments for the Resource 1 and 2 deposits water management system at Troy Resources’ Karouni Mine (Karouni). Advanced pre-feasibility level recommendations for pit development were provided based on benchmarking…

VIEW PROJECT

San Andrés Mine

Previous to Tierra Group, our Team performed a geotechnical forensics assessment, which determined that spent ore from an on-off leach pad operation had liquefied causing a debris flow, which threatened inundating a major river basin. A preventative detention buttress was…

VIEW PROJECT

Fekola Project

Tierra Group provided earthworks and concrete Construction Quality Control (CQC) services for B2Gold's Fekola Mine in western Mali. Tierra Group overcame the remote location and kept a dedicated team on-site throughout the 2-year mine development. Tierra Group assisted Fekola Mine…

VIEW PROJECT

Campo Morado Mine

Tierra Group performed a Dam Safety Review (DSR) for Nyrstar’s tailings storage facility (TSF) located in Campo Morado (Guerrero, Mexico).  Tierra Group served as the Tailings Reviewer to ensure conformity with local regulations, the Nyrstar Tailings Storage Facility (TSF) Standard,…

VIEW PROJECT

La India Mine

Tierra Group performed geotechnical investigation, water balance, and the Phase 2 heap leach pad (HLP) optimization design at Agnico Eagle’s La India Mine in Sonora State Mexico. Tierra Group provided Construction Quality Assurance (CQA) during initial construction and expansion of…

VIEW PROJECT

Hollister Waste Rock Facility

Hollister Waste Rock Facility Storage Tierra Group performed a third-party peer review of a Waste Rock Storage Facility (WRSF) design at Klondex Mines’ (Klondex) Hollister Mine in northern Nevada. The WRSF, as designed, involved lining the mine’s existing West Pit…

VIEW PROJECT