Stibnite Gold Project

Project Highlights:

  • Tailings Storage Facility (TSF) Design
  • Geotechnical Engineering
  • Civil Engineering
  • Hydrology
  • Water Balance
  • Pre-feasibility Study
  • Diversion Design
  • Feasibility Study Support
  • Permitting Support (NEPA & State)
  • Reclamation Cost Estimating (SRCE)

The Stibnite project is located in the remote central Idaho Rockies near the town of Yellow Pine.  It is a brownfields gold-antimony project featuring three open pits and an anticipated 22,000 tpd plant throughput, along with challenging terrain and environmental constraints. Tierra Group completed the preliminary feasibility design for the proposed tailings storage facility, water diversions, and site-wide water management, including relevant content for the NI-43-101-compliant prefeasibility technical report. Tierra Group also completed TSF and water diversion designs and completed reclamation cost estimating for a NI 43-101 compliant feasibility study published in January 2020. Tierra Group also completed engineering analyses and design for federal and state permitting.

The TSF was lined with a composite geosynthetic liner system. A rockfill buttress was built in multiple stages during project development. Diversions redirected a perennial mountain stream around the TSF. Tierra Group continues supporting Midas by completing detailed design and permitting support.

Project Highlights:

  • Tailings Storage Facility (TSF) Design
  • Geotechnical Engineering
  • Civil Engineering
  • Hydrology
  • Water Balance
  • Pre-feasibility Study
  • Diversion Design
  • Feasibility Study Support
  • Permitting Support (NEPA & State)
  • Reclamation Cost Estimating (SRCE)

Similar projects

Fire Creek Mine

Tierra Group conducted a siting analysis for a new WRSF to support the mine’s future production increase as part of the Preliminary Feasibility Study (PFS). In addition to supporting the PFS, Tierra Group assisted in preparing and submitting several engineering…

VIEW PROJECT

American Gypsum

American Gypsum Pit Planning and Support Tierra Group began working at American Gypsum’s Eagle-Gypsum mine located in Gypsum, Colorado in 2014 evaluating haul road improvements. A trade-off study provided a tool for American Gypsum to evaluate safety improvements including alternative haul road…

VIEW PROJECT

La India Mine

GoldSim Training Tierra Group provided GoldSim training to the Agnico Team and updated the heap leach water balance. Phase 2 & 3 Heap Leach Pad Design and Construction Quality Assurance Tierra Group provided engineering design services for the Phase 2 and 3…

VIEW PROJECT

Tailings Assurance Audit | Canada

Tierra Group completed a Tailings Assurance Audit (TAA) for a closed Tailings Storage Facility (TSF). The TAA was completed to ensure the TSF and site operations complied with the Company's Tailings Management Standard, which closely mirrors Global Industry Standard on…

VIEW PROJECT

Ray Mine

Tierra Group is implementing a corporate Tailings Stewardship Strategy (TSS) at all of ASARCO Grupo Mexico’s mines in Arizona, USA (Hayden, Mission and Ray mines). Tierra Group conducted a site visit to each site to perform dam safety inspections, interview…

VIEW PROJECT

Caeté Complex

Tierra Group developed a site-wide water management plan, and performed a liquefaction potential study following the Samarco tailings dam failure in Minas Gerais, Brazil. A tailings storage facility water balance was developed to optimize water usage and minimize risks at…

VIEW PROJECT

Sterling Mine

Sterling Mine is an underground gold mine in southern Nevada which recovers gold through heap leaching and a carbon adsorption-desorption-recovery (ADR) plant. Tierra Group team members have a long history at Sterling, starting with heap leach pad final permanent closure…

VIEW PROJECT

Karouni Mine

Tierra Group reviewed and provided pit slope recommendations and conducted hydrological assessments for the Resource 1 and 2 deposits water management system at Troy Resources’ Karouni Mine (Karouni). Advanced pre-feasibility level recommendations for pit development were provided based on benchmarking…

VIEW PROJECT

Orotex Mine Project

Tierra Group provided tailings engineering design and consulting services for the redevelopment of the Orotex underground mine in Alajuela, Costa Rica. Tierra Group's areas of responsibility included tailings and water management in this environmentally sensitive, high rainfall, tropical, mountainous region.

VIEW PROJECT

Tailings Review & Assurance Audit | Montana

Tailings Management Assurance Review Tierra Group served as the Lead Auditor and conducted MARs for the TSFs at this confidential project. Tierra Group reviewed all available facility documentation, including OMS Manuals, EAPs, design reports, As-Built Reports, annual inspection reports, and other…

VIEW PROJECT

La Negra Mine

Tierra Group performed a tailings storage facility safety (TSF) audit for the 90 m high upstream constructed tailings dam at La Negra Mine in Querétaro, Mexico. The project included a TSF dam inspection and Dam Safety Inspection Report (DSIR) containing operational…

VIEW PROJECT

Quinsam Coal

Tierra Group served as an independent subject matter expert for the Quinsam Coal Corporation (QCC) Independent Tailings Review Board (ITRB) in British Columbia, Canada. The annual review process included review of existing documents, a site visit, and collaborative meetings with…

VIEW PROJECT