Tierra Group completed a Tailings Assurance Audit (TAA) for a closed Tailings Storage Facility (TSF). The TAA was completed to ensure the TSF and site operations complied with the Company's Tailings Management Standard, which closely mirrors Global Industry Standard on Tailings Management (GISTM) requirements. The TAA included a site visit, document review, and interviews with site personnel to determine compliance.
Tierra Group represented Oracle Ridge Mining as the Qualified Person for portions of the feasibility-level design including the Dry Stack Tailings Storage Facility (TSF) Design, Site-Wide Stormwater Management, Water Supply Pipelines, Haul Road and Access Road Design Improvements, and the…
Dry Stack Tailings Storage Facility Tierra Group designed a dry stack TSF to store excess tailings from the underground paste backfill. The dry stack TSF was challenging, given the limited land area, steep terrain, seasonal cold weather, and surface water…
Tierra Group conducted a Preliminary Site Assessment of a potential large-scale landslide near the El Diamante Hydropower Complex in Matagalpa, Nicaragua.
Tierra Group performed Dam Safety Reviews (DSRs) for Nyrstar’s tailings storage facilities (TSFs) located in Tennessee, United States. Tierra Group served as the Tailings Reviewer to ensure conformity with local regulations, the Nyrstar Tailings Storage Facility (TSF) Standard, and to…
Tierra Group performed an independent engineering design review of a Cemented Tailings Facility (CTF) and multiple processes and freshwater ponds. Tailings will be mixed with cement at the paste plant and deposited in the CTF along with underground mine development…
Tierra Group conducted an update of the Mexican Hat Project’s Preliminary Economic Assessment. Tierra Group’s update included the heap leach facility design and preliminary stacking plan, waste rock storage pad, and crushed rock storage pad design.
Tierra Group prepared a Heap Leach Facility (HLF) design to an FS level, including a geotechnical investigation, HLF design basis and criteria, hydrology and water balance, geotechnical engineering analysis, specifications, material quantities, and design report. In addition, Tierra Group prepared…
Hollister Waste Rock Facility Storage Tierra Group performed a third-party peer review of a Waste Rock Storage Facility (WRSF) design at Klondex Mines’ (Klondex) Hollister Mine in northern Nevada. The WRSF, as designed, involved lining the mine’s existing West Pit…
Tierra Group completed a geotechnical investigation, which included overseeing hollow stem auger (HSA) drilling and laboratory testing, that characterized the existing earthen dam. Tierra Group completed a low-level outlet structure design that was believed to have been compromised by internal…
Tierra Group provides Tailings Stewardship Services for Nyrstar's Myra Falls Mine Tailings Storage Facility. Tierra Group performed a 5-year Dam Safety Review consistent with the Canadian Dam Association protocols, site training and in depth inspections of management practices and facilities…
Tierra Group conducted a siting analysis for a new WRSF to support the mine’s future production increase as part of the Preliminary Feasibility Study (PFS). In addition to supporting the PFS, Tierra Group assisted in preparing and submitting several engineering…
Tierra Group provided a feasibility-level Tailings Storage Facility (TSF) design for Condor Gold’s La India Project permitting, a planned 2,000 tpd open pit mine in western Nicaragua. TSF embankments used rockfill from the open pit and a geomembrane liner for…