Project Highlights:

  • Independent Engineering Review
  • Tailings Storage Facilities
  • Tailings Assurance Audit

Tailings Management Assurance Review

Tierra Group served as the Lead Auditor and conducted MARs for the TSFs at this confidential project. Tierra Group reviewed all available facility documentation, including OMS Manuals, EAPs, design reports, As-Built Reports, annual inspection reports, and other relevant documentation in determining each site’s compliance with the Company’s Tailings and Heap Leach Management Standard.

Independent Engineer's Review

Tierra Group personnel served as the Audit Lead to review tailings management procedures and compared them to standards outlined in the Company’s Corporate Tailings and Heap Leach Management Standard.

Tailings Assurance Audit

Tierra Group completed a Tailings Assurance Audit (TAA) for Tailings Storage Facility 2 (TSF2). The TAA was completed to ensure the TSF and site operations complied with the Company’s Tailings Management Standard, which closely mirrors Global Industry Standard on Tailings Management (GISTM) requirements. 

Project Highlights:

  • Independent Engineering Review
  • Tailings Storage Facilities
  • Tailings Assurance Audit

Similar projects

Copperstone Project

Tierra Group International, Ltd. participated as the geotechnical lead engineering firm for the Copperstone Project Pre-Feasibility Study (PFS) in Arizona, U.S.A. Tierra Group was responsible for tailings and waste rock storage, water management and underground geotechnics design and cost estimates…

VIEW PROJECT

Los Gatos Project

TSF Design and CQA Tierra Group provided detailed Stage 1 and 2 Tailings Storage Facility design, conducted a process plant geotechnical foundation investigation, and provided Construction Quality Assurance for Sunshine Silver Mining's Los Gatos Project in Chihuahua, Mexico. Tierra Group then…

VIEW PROJECT

Sweetwater Mine

Sweetwater Mine Permitting Tierra Group’s Team began work at the Sweetwater mine in 1993 assisting permitting and developing tailings impoundment management strategies for the mine. We successfully designed and installed an innovative internal seal for repair of the mine’s damaged…

VIEW PROJECT

Midas Mine

The Midas Mine is located in northern Nevada, and is owned and operated by Hecla Mining Company.  The mine is an underground mine with an operating mill. The mine’s existing tailings facilities are nearing their end of operating life and…

VIEW PROJECT

Midas Gold Project

Midas Gold’s project is located in the remote central Idaho Rockies near the town of Yellow Pine.  It is a brownfields gold-antimony project featuring three open pits and an anticipated 22,000 tpd plant throughput, along with challenging terrain and environmental…

VIEW PROJECT

Pierina Mine

Barrick Gold Corporation’s Pierina Mine in Ancash Department, Perú began operations in 1998. A progressive reclamation and closure plan began in 2013.  In 2015-16 Tierra Group developed detailed engineering designs for channels, sediment traps, two 45,000 m3 sediment ponds, water…

VIEW PROJECT

Mission Mine

Tierra Group is implementing a corporate Tailings Stewardship Strategy (TSS) at all of ASARCO Grupo Mexico’s mines in Arizona, USA (Hayden, Mission and Ray mines). Tierra Group conducted a site visit to each site to perform dam safety inspections, interview…

VIEW PROJECT

Lost Creek Project | USA

Tierra Group is assisting Millcreek Mining and Black Mountain Sand with the preparation of permitting documents for the Lost Creek Project; including a preliminary Stormwater Management Plan, preliminary Groundwater Monitoring Plan, and general permitting exhibits. Tierra Group conducted a site geotechnical…

VIEW PROJECT

Hollister Waste Rock Facility

Hollister Waste Rock Facility Storage Tierra Group performed a third-party peer review of a Waste Rock Storage Facility (WRSF) design at Klondex Mines’ (Klondex) Hollister Mine in northern Nevada. The WRSF, as designed, involved lining the mine’s existing West Pit…

VIEW PROJECT

2020 TSF Annual Dam Inspection

Tierra Group completed an annual dam safety inspection (DSI) to meet both Nevada Division of Water Resources (NDWR) Dam Safety and the client's requirements. The DSI included reviewing monitoring data, a dam and appurtenant structures inspection, and a DSI report.

VIEW PROJECT

Esmeralda Mill

Tierra Group was contracted by Waterton Global Mining Company to prepare the FPCP for TSF No.1 at the Esmeralda Mine. TSF No.1 covered approximately 100 acres, included a rockfill embankment with a maximum height approximately 60 feet, and stored gold tailings. Work…

VIEW PROJECT

La Trinidad

Tierra Group began work at La Trinidad providing heap leach pad construction recommendations and a water balance. Tierra Group continued support with a heap leach pad expansion design, slope stability analyses, hydrologic analyses, diversion design, liner design, and leach solution…