Sweetwater Mine

Project Highlights:

  • Permitting
  • Tailings Operations Planning
  • CQA
  • Liquefaction
  • Seismic Stability
  • Slope Stability Analysis
  • Engineer of Record
  • Conventional Tailings

Sweetwater Mine Permitting

Tierra Group’s Team began work at the Sweetwater mine in 1993 assisting permitting and developing tailings impoundment management strategies for the mine. We successfully designed and installed an innovative internal seal for repair of the mine’s damaged decant discharge conduit. Tierra Group began working at Sweetwater again in 2015 designing a 5 foot TSF dam and spillway raise. Unique design challenges were overcome with a comprehensive field investigation including CPT and hollow stem auger drilling. Liquefaction analyses were performed and incorporated into the upstream raise design. A challenging hydrology model was completed and a raise to the existing spillway was designed. The raise design was approved by MDNR Dam and Reservoir Safety council in March 2016. Construction was completed in early 2017 with support provided with Tierra Group overseeing construction activities and evaluating proposed design changes. An As-Built report was completed in April 2017 conforming to MDNR requirements. Tierra Group provided additional support at Sweetwater by designing a 23 foot dam raise providing more than 15 years additional tailings capacity. A new spillway and saddle dam was included in the design. The dam raise design was approved by MDNR in July 2018. Tierra Group supported dam raise construction in 2021 completing design optimizations that reduced construction costs, supporting construction, and completing an as-built report.

Project Highlights:

  • Permitting
  • Tailings Operations Planning
  • CQA
  • Liquefaction
  • Seismic Stability
  • Slope Stability Analysis
  • Engineer of Record
  • Conventional Tailings

Similar projects

Goldfield Bonanza Project

Lode-Star Gold, Inc., in advance of their proposed mining operations, submited a Physical Separation Facility application with the State of Nevada for their Goldfield Bonanza Project located in Esmeralda County, Nevada. The mine, located in the historic high-grade gold-bearing district of…

VIEW PROJECT

La India Mine - CQA HLF Phase 3

Tierra Group performed Construction Quality Assurance (CQA) services for heap leach expansion Phase 3.

VIEW PROJECT

Goldstrike Mine

Engineer of Record Barrick’s Goldstrike Mine processes 30,000 tons of gold ore per day from its combined open-pit/underground operations located in the historic Carlin Trend in Nevada, U.S.A. Goldstrike’s tailings are stored in the North Block Tailings Disposal Facility (NBTDF).…

VIEW PROJECT

Brushy Creek 2

Tierra Group was commissioned by Doe Run to design a new tailings storage facility at the Brushy Creek Mine. Tierra Group completed a geotechnical investigation including boring, classifying, and sampling soil and rock. Trade-off studies were performed to minimize construction…

VIEW PROJECT

Rhyolite Ridge

Tierra Group is providing water management and geotechnical engineering services to support a Preliminary Feasibility Study at the Rhyolite Ridge Lithium Mine Project in Nevada.

VIEW PROJECT

Black Butte Copper Project

Tierra Group performed a third-party design review of a Cemented Tailings Facility (CTF) and multiple process and freshwater ponds. Tailings will be mixed with cement at the planned paste plant and deposited in the CTF along with underground mine development…

VIEW PROJECT

Midas Mine

The Midas Mine is located in northern Nevada, and is owned and operated by Klondex Mines LTD.  The mine is an underground mine with an operating mill. The mine’s existing tailings facilities are nearing their end of operating life and…

VIEW PROJECT

La Negra Mine

Tierra Group performed a tailings storage facility safety (TSF) audit for the 90 m high upstream constructed tailings dam at La Negra Mine in Querétaro, Mexico. The project included a TSF dam inspection and Dam Safety Inspection Report (DSIR) containing operational…

VIEW PROJECT

Equity Silver ITRB

Tierra Group's Matt Fuller, LEG, P.Geo. serves as one of three ITRB technical experts providing technical assurance of the Engineer of Record’s design and monitoring compliance with BC regulations, the Newmont Corporate Tailings Standard, and industry best practices.

VIEW PROJECT

Collection Pond Washdown Pad IFC Set

Tierra Group designed a concrete washdown pad connecting to the site’s existing collection pond. The pad was designed to allow the site to wash vehicles prior to them being approved to leave site.

VIEW PROJECT

New Jersey Mill TSF Scoping Study

Tierra Group completed the design for two 3-meter upstream raises to an existing paste tailings storage facility at New Jersey Mining Company’s New Jersey Mill site near Kellogg, Idaho. Work included performing a cone penetration testing (CPT) investigation of the…

VIEW PROJECT

Minera Plata Real | Los Gatos TSF Phase 2

Tierra Group designed a raise of the tailings storage facility (TSF) and provided construction quality assurance for the Los Gatos project in Chihuahua, Mexico.

VIEW PROJECT