Sweetwater Mine

Project Highlights:

  • Permitting
  • Tailings Operations Planning

Sweetwater Mine Permitting

Tierra Group’s Team began work at the Sweetwater mine in 1993 assisting permitting and developing tailings impoundment management strategies for the mine. We successfully designed and installed an innovative internal seal for repair of the mine’s damaged decant discharge conduit. Tierra Group began working at Sweetwater again in 2015 designing a 5 foot TSF dam and spillway raise. Unique design challenges were overcome with a comprehensive field investigation including CPT and hollow stem auger drilling. Liquefaction analyses were performed and incorporated into the upstream raise design. A challenging hydrology model was completed and a raise to the existing spillway was designed. The raise design was approved by MDNR Dam and Reservoir Safety council in March 2016. Construction was completed in early 2017 with support provided with Tierra Group overseeing construction activities and evaluating proposed design changes. An As-Built report was completed in April 2017 conforming to MDNR requirements. Tierra Group provided additional support at Sweetwater by developing a deposition plan, water balance, hydrology study, and geotechnical modeling to design an additional tailings dam raise.

Project Highlights:

  • Permitting
  • Tailings Operations Planning

Similar projects

Hecla WWR 5840’ Raise EDC

Tierra Group prepared an engineering design change to increase the maximum elevation permitted for the mine’s existing WWR. Project included a waste rock dump expansion civil design and stability modeling to verify design complied with regulatory dam safety criteria.

VIEW PROJECT

Stillwater Mining Company

Tierra Group performed a TSF Design Review to support a NI 43-101 compliant Feasibility Study. The TSF design incorporated a paste tailings disposal method in an environmentally sensitive fisheries habitat in south-central Montana.

VIEW PROJECT

Brushy Creek 2

Tierra Group was commissioned by Doe Run to design a new tailings storage facility at the Brushy Creek Mine. Tierra Group completed a geotechnical investigation including boring, classifying, and sampling soil and rock. Trade-off studies were performed to minimize construction…

VIEW PROJECT

Isabella Pearl

Tierra Group performed a technical peer review of the Isabella Pearl heap leach facility (HLF) owned by Gold Resource Corporation. Isabella Pearl mine is located at the west end of the Santa Fe mining district in the Walker Lane gold…

VIEW PROJECT

Geotechnical Service for Area 2000

Tierra Group completed a collection of geomechanical field data (Inspections, mappings, sampling, testing, among others) for the tunnels, plant-mine road, areas at the base of the dump, access to tailings dam, truck shop slopes, bypass, and non-permanent accesses. The works…

VIEW PROJECT

Gediktepe Peer Review

Tierra Group provided technical direction and review of the Gediktepe Heap Leach Facility (HLF), ponds, and waste rock dump facility designs. Tierra Group will also provide CQA review during HLF construction.

VIEW PROJECT

Pitarrilla Mine

Tierra Group participated as a member of a multi-disciplinary project team to develop a Definitive Feasibility study for a 16,000 tpd silver mine in Durango, Mexico. Tierra Group's responsibilities included designing a 112 Mt tailings storage facility, developing a site-wide…

VIEW PROJECT

Amulsar Gold Project

Tierra Group completed a technical review of the heap leach pad for the Amulsar Mine property owned by Lydian Armenia located near the town of Jermuk to the southeast of Armenia. The heap leach pad consists of four phases with…

VIEW PROJECT

Antapaccay

Glencore’s Antapaccay mine is located in the Espinar province, Cuzco, Perú. Tierra Group logged geotechnical, geological and geo-mechanical properties of drill core advanced in Antapaccay's Northern Pit. Approximately 6,000 meters of core were logged. Specific samples were selected for geotechnical…

VIEW PROJECT

San Albino Dry Stack Tailings Storage Facility Design

Tierra Group supported construction of the San Albino Mine in Nueva Segovia, Nicaragua. Tierra Group designed a dry stack drum filtered-tailings storage facility. A siting study optimized the dry stack location and minimized CAPEX and OPEX. Tierra Group developed a site-wide water…

VIEW PROJECT

Sweetwater Mine

Sweetwater Mine Permitting Tierra Group’s Team began work at the Sweetwater mine in 1993 assisting permitting and developing tailings impoundment management strategies for the mine. We successfully designed and installed an innovative internal seal for repair of the mine’s damaged…

VIEW PROJECT

Buritic√° Tailings Stewardship & Cyanide Speciation

Tierra Group provided Tailings Stewardship Services for Continental Gold’s Buriticá Project in Antioquia, Columbia which included permitting support, Third-Party Review and construction and operations support. Tierra Group oversaw the development of a 2D hydrodynamic model to support the design of…

VIEW PROJECT