Sweetwater Mine

Project Highlights:

  • Permitting
  • Tailings Operations Planning
  • CQA
  • Liquefaction
  • Seismic Stability
  • Slope Stability Analysis
  • Engineer of Record
  • Conventional Tailings

Sweetwater Mine Permitting

Tierra Group’s Team began work at the Sweetwater mine in 1993 assisting permitting and developing tailings impoundment management strategies for the mine. We successfully designed and installed an innovative internal seal for repair of the mine’s damaged decant discharge conduit. Tierra Group began working at Sweetwater again in 2015 designing a 5 foot TSF dam and spillway raise. Unique design challenges were overcome with a comprehensive field investigation including CPT and hollow stem auger drilling. Liquefaction analyses were performed and incorporated into the upstream raise design. A challenging hydrology model was completed and a raise to the existing spillway was designed. The raise design was approved by MDNR Dam and Reservoir Safety council in March 2016. Construction was completed in early 2017 with support provided with Tierra Group overseeing construction activities and evaluating proposed design changes. An As-Built report was completed in April 2017 conforming to MDNR requirements. Tierra Group provided additional support at Sweetwater by designing a 23 foot dam raise providing more than 15 years additional tailings capacity. A new spillway and saddle dam was included in the design. The dam raise design was approved by MDNR in July 2018. Tierra Group supported dam raise construction in 2021 completing design optimizations that reduced construction costs, supporting construction, and completing an as-built report.

Project Highlights:

  • Permitting
  • Tailings Operations Planning
  • CQA
  • Liquefaction
  • Seismic Stability
  • Slope Stability Analysis
  • Engineer of Record
  • Conventional Tailings

Similar projects

Rosario Mine

Tierra Group performed a Dam Safety Review (DSR) including geotechnical investigations and seepage and slope stability analyses for a 20-m high TSF at this 300‑tpd underground polymetallic mine. The audit was prepared following the Mt. Polley tailings dam failure in…

VIEW PROJECT

El Diamante Hydropower Dam

Tierra Group conducted a Preliminary Site Assessment of a potential large-scale landslide near the El Diamante Hydropower Complex in Matagalpa, Nicaragua.

VIEW PROJECT

Aurora Mine

The Aurora Mine Mill Facility (previously Esmeralda Mill) is located in the historic Aurora mining district of the eastern Sierra Nevada Mountain Range in Nevada, USA. Aurora recently, with the support of Tierra Group completed a Minor Modification to the…

VIEW PROJECT

Douglas County, CO | 2020 Stormwater Support

Tierra Group provided engineering and permitting support to Douglas County Public Works Engineering for NPDES Phase II Program compliance. Tierra Group’s scope of work included developing Runoff Control Plans (RCPs) for new County facilities, updating RCPs at existing County facilities,…

VIEW PROJECT

Isabella Pearl

Tierra Group performed a technical peer review of the Isabella Pearl heap leach facility (HLF) owned by Gold Resource Corporation. Isabella Pearl mine is located at the west end of the Santa Fe mining district in the Walker Lane gold…

VIEW PROJECT

La India Mine

GoldSim Training Tierra Group provided GoldSim training to the Agnico Team and updated the heap leach water balance. Phase 2 & 3 Heap Leach Pad Design and Construction Quality Assurance Tierra Group provided engineering design services for the Phase 2 and 3…

VIEW PROJECT

Candelones Oxide Project | Heap Leach Feasibility Design

Tierra Group prepared a Heap Leach Facility (HLF) design to an FS level, including a geotechnical investigation, HLF design basis and criteria, hydrology and water balance, geotechnical engineering analysis, specifications, material quantities, and design report. In addition, Tierra Group prepared…

VIEW PROJECT

El Mochito Mine

El Mochito is an underground zinc/silver mine located in the Santa Barbara Mountains in north-central Honduras. Tierra Group’s Team has been providing Tailings Stewardship Services at El Mochito continuously for the past 26 years. Since 1989, Tierra Group engineers have provided…

VIEW PROJECT

Sepon Mine CQA

Tierra Group performed Resident Engineering and Construction Quality Control/Assurance during a pilot Heap Leach Facility construction, and Life of Mine Heap Leach and Tailings Sorage Facility siting, design, and tailings management at Lane Xang Minerals' Sepon Mine in Laos.

VIEW PROJECT

Brushy Creek 2

Tierra Group was commissioned by Doe Run to design a new tailings storage facility at the Brushy Creek Mine. Tierra Group completed a geotechnical investigation including boring, classifying, and sampling soil and rock. Trade-off studies were performed to minimize construction…

VIEW PROJECT

Fire Creek Mine

Tierra Group conducted a siting analysis for a new WRSF to support the mine’s future production increase as part of the Preliminary Feasibility Study (PFS). In addition to supporting the PFS, Tierra Group assisted in preparing and submitting several engineering…

VIEW PROJECT

Karouni Mine

Tierra Group reviewed and provided pit slope recommendations and conducted hydrological assessments for the Resource 1 and 2 deposits water management system at Troy Resources’ Karouni Mine (Karouni). Advanced pre-feasibility level recommendations for pit development were provided based on benchmarking…

VIEW PROJECT