Sweetwater Mine

Project Highlights:

  • Permitting
  • Tailings Operations Planning

Sweetwater Mine Permitting

Tierra Group’s Team began work at the Sweetwater mine in 1993 assisting permitting and developing tailings impoundment management strategies for the mine. We successfully designed and installed an innovative internal seal for repair of the mine’s damaged decant discharge conduit. Tierra Group began working at Sweetwater again in 2015 designing a 5 foot TSF dam and spillway raise. Unique design challenges were overcome with a comprehensive field investigation including CPT and hollow stem auger drilling. Liquefaction analyses were performed and incorporated into the upstream raise design. A challenging hydrology model was completed and a raise to the existing spillway was designed. The raise design was approved by MDNR Dam and Reservoir Safety council in March 2016. Construction was completed in early 2017 with support provided with Tierra Group overseeing construction activities and evaluating proposed design changes. An As-Built report was completed in April 2017 conforming to MDNR requirements. Tierra Group provided additional support at Sweetwater by developing a deposition plan, water balance, hydrology study, and geotechnical modeling to design an additional tailings dam raise.

Project Highlights:

  • Permitting
  • Tailings Operations Planning

Similar projects

Anaconda Mine

Tailings Storage Trade-Off Study Tierra Group completed trade-off studies evaluating potential TSF sites to store 25 million tonnes of tailings. Trade-off studies included dam layouts, cost estimating, and recommendations for future work. Trade-off study challenges were minimizing costs while still…

VIEW PROJECT

Karouni Mine, Hicks 4 Phase 2

Tierra Group conducted a slope stability analysis for Troy Resources’ Hicks 4 Phase 2 North Wall Failure and provided recommendations for stable pit configurations.

VIEW PROJECT

La Libertad Mine

Tierra Group engineers designed La Esperanza TSF, a 2.1-km long, 35-m high, earthfill tailings dam with an HDPE lined impoundment footprint of 840,000 m2. Tierra Group  designed and provided Construction Quality Assurance (CQA) for all subsequent downstream dam stages. Stage…

VIEW PROJECT

Midas Mine

The Midas Mine is located in northern Nevada, and is owned and operated by Klondex Mines LTD.  The mine is an underground mine with an operating mill. The mine’s existing tailings facilities are nearing their end of operating life and…

VIEW PROJECT

Goldstrike Mine

Engineer of Record Barrick’s Goldstrike Mine processes 30,000 tons of gold ore per day from its combined open-pit/underground operations located in the historic Carlin Trend in Nevada, U.S.A. Goldstrike’s tailings are stored in the North Block Tailings Disposal Facility (NBTDF).…

VIEW PROJECT

Copperstone Project

Tierra Group International, Ltd. participated as the geotechnical lead engineering firm for the Copperstone Project Pre-Feasibility Study (PFS) in Arizona, U.S.A. Tierra Group was responsible for tailings and waste rock storage, water management and underground geotechnics design and cost estimates…

VIEW PROJECT

Hod Mine Waste Dump and Surface Water Management Design

Tierra Group provided design review and technical direction at Hod Mine in the Artvin Province of Turkey. Work included detailed design of potentially acid generating and non-acid generating waste dump facilities, their appurtenant structures and stormwater management design for the…

VIEW PROJECT

Amulsar Gold Project

Tierra Group completed a technical review of the heap leach pad for the Amulsar Mine property owned by Lydian Armenia located near the town of Jermuk to the southeast of Armenia. The heap leach pad consists of four phases with…

VIEW PROJECT

Douglas County Public Works

Tierra Group updated the County’s Standard Operating Procedures (SOPs) for Municipal Operations to maintain the County’s compliance with the requirements for stormwater discharges from the County’s municipal separate storm sewer system (MS4) under the Colorado Discharge Permit System (CDPS). Tierra…

VIEW PROJECT

Fekola Project

Tierra Group provided earthworks and concrete Construction Quality Control (CQC) services for B2Gold's Fekola Mine in western Mali. Tierra Group overcame the remote location and kept a dedicated team on-site throughout the 2-year mine development. Tierra Group assisted Fekola Mine…

VIEW PROJECT

Buenaventura Photogrammetry Study for El Brocal Mine

Tierra Group developed a photogrammetry study and basic civil design for mining facilities layout at El Brocal Mine.

VIEW PROJECT

Midas Gold Project

Midas Gold’s project is located in the remote central Idaho Rockies near the town of Yellow Pine.  It is a brownfields gold-antimony project featuring three open pits and an anticipated 22,000 tpd plant throughput, along with challenging terrain and environmental…

VIEW PROJECT