Sweetwater Mine

Project Highlights:

  • Permitting
  • Tailings Operations Planning
  • CQA
  • Liquefaction
  • Seismic Stability
  • Slope Stability Analysis
  • Engineer of Record
  • Conventional Tailings

Sweetwater Mine Permitting

Tierra Group’s Team began work at the Sweetwater mine in 1993 assisting permitting and developing tailings impoundment management strategies for the mine. We successfully designed and installed an innovative internal seal for repair of the mine’s damaged decant discharge conduit. Tierra Group began working at Sweetwater again in 2015 designing a 5 foot TSF dam and spillway raise. Unique design challenges were overcome with a comprehensive field investigation including CPT and hollow stem auger drilling. Liquefaction analyses were performed and incorporated into the upstream raise design. A challenging hydrology model was completed and a raise to the existing spillway was designed. The raise design was approved by MDNR Dam and Reservoir Safety council in March 2016. Construction was completed in early 2017 with support provided with Tierra Group overseeing construction activities and evaluating proposed design changes. An As-Built report was completed in April 2017 conforming to MDNR requirements. Tierra Group provided additional support at Sweetwater by designing a 23 foot dam raise providing more than 15 years additional tailings capacity. A new spillway and saddle dam was included in the design. The dam raise design was approved by MDNR in July 2018. Tierra Group supported dam raise construction in 2021 completing design optimizations that reduced construction costs, supporting construction, and completing an as-built report.

Project Highlights:

  • Permitting
  • Tailings Operations Planning
  • CQA
  • Liquefaction
  • Seismic Stability
  • Slope Stability Analysis
  • Engineer of Record
  • Conventional Tailings

Similar projects

Turmalina Complex

Tierra Group developed a site-wide water management plan to improve operational water usage and management at Jaguar Mining's Turmalina Complex in Minas Gerais, Brazil. Turmalina is a zero-discharge facility that required optimizing tailings supernatant usage in the process, enhanced evaporation…

VIEW PROJECT

Brushy Creek 2

Tierra Group was commissioned by Doe Run to design a new tailings storage facility at the Brushy Creek Mine. Tierra Group completed a geotechnical investigation including boring, classifying, and sampling soil and rock. Trade-off studies were performed to minimize construction…

VIEW PROJECT

Mt. Todd Dam Assessment

Tierra Group conducted an Independent Technical review of Vista Gold Corp’s Mt. Todd Tailings Storage Facility Expansion in Northern Territory, Australia. Tierra Group assisted the 2025 Mt. Todd feasibility study project providing TSF and waste rock dump design and water…

VIEW PROJECT

San Andrés Mine

Previous to Tierra Group, our Team performed a geotechnical forensics assessment, which determined that spent ore from an on-off leach pad operation had liquefied causing a debris flow, which threatened inundating a major river basin. A preventative detention buttress was…

VIEW PROJECT

Anaconda Mine

Tailings Storage Trade-Off Study Tierra Group completed trade-off studies evaluating potential TSF sites to store 25 million tonnes of tailings. Trade-off studies included dam layouts, cost estimating, and recommendations for future work. Trade-off study challenges were minimizing costs while still…

VIEW PROJECT

Robinson Mine

Robinson Mine Tailings Impoundment Audit Prior to joining Tierra Group, our Team completed a third-party tailings impoundment audit. The audit included reviewing operational procedures, monitoring, design, and future tailings storage planning. Produced an audit report for company’s internal use. (Tetra Tech,…

VIEW PROJECT

El Gallo Mine

El Gallo is a 3,000 tpd open-pit gold/silver mine located in the foothills of the Sierra Madre Mountain Range in Mexico’s Sinaloa State. Gold is recovered through heap leaching and adsorption/desorption/recovery (ADR). Production commenced at El Gallo with the first gold pour in September…

VIEW PROJECT

Lagunas Norte Mine

The Lagunas Norte Mine, operated by Barrick Misquichilca S.A., is an open pit gold mine located in the Quiruvilca district, Santiago de Chuco province, La Libertad department, Perú. The main study objective was to evaluate the volume of effluent discharge…

VIEW PROJECT

Tailings Assurance Audit | Canada

Tierra Group completed a Tailings Assurance Audit (TAA) for a closed Tailings Storage Facility (TSF). The TAA was completed to ensure the TSF and site operations complied with the Company's Tailings Management Standard, which closely mirrors Global Industry Standard on…

VIEW PROJECT

Amulsar Gold Project

Tierra Group completed a technical review of the heap leach pad for the Amulsar Mine property owned by Lydian Armenia located near the town of Jermuk to the southeast of Armenia. The heap leach pad consists of four phases with…

VIEW PROJECT

Tajo Crimea Project

Tierra Group evaluated the Tajo Crimea Pit’s geotechnical and hydrogeological characteristics to determine in-pit tailings storage feasibility. The project scope defined geotechnical and hydrogeologic site conditions through field investigations and in-situ pump testing. Tierra Group developed a 3D groundwater model…

VIEW PROJECT

Midas Mine

The Midas Mine is located in northern Nevada, and is owned and operated by Hecla Mining Company.  The mine is an underground mine with an operating mill. The mine’s existing tailings facilities are nearing their end of operating life and…

VIEW PROJECT