Sweetwater Mine

Project Highlights:

  • Permitting
  • Tailings Operations Planning
  • CQA
  • Liquefaction
  • Seismic Stability
  • Slope Stability Analysis
  • Engineer of Record
  • Conventional Tailings

Sweetwater Mine Permitting

Tierra Group’s Team began work at the Sweetwater mine in 1993 assisting permitting and developing tailings impoundment management strategies for the mine. We successfully designed and installed an innovative internal seal for repair of the mine’s damaged decant discharge conduit. Tierra Group began working at Sweetwater again in 2015 designing a 5 foot TSF dam and spillway raise. Unique design challenges were overcome with a comprehensive field investigation including CPT and hollow stem auger drilling. Liquefaction analyses were performed and incorporated into the upstream raise design. A challenging hydrology model was completed and a raise to the existing spillway was designed. The raise design was approved by MDNR Dam and Reservoir Safety council in March 2016. Construction was completed in early 2017 with support provided with Tierra Group overseeing construction activities and evaluating proposed design changes. An As-Built report was completed in April 2017 conforming to MDNR requirements. Tierra Group provided additional support at Sweetwater by designing a 23 foot dam raise providing more than 15 years additional tailings capacity. A new spillway and saddle dam was included in the design. The dam raise design was approved by MDNR in July 2018. Tierra Group supported dam raise construction in 2021 completing design optimizations that reduced construction costs, supporting construction, and completing an as-built report.

Project Highlights:

  • Permitting
  • Tailings Operations Planning
  • CQA
  • Liquefaction
  • Seismic Stability
  • Slope Stability Analysis
  • Engineer of Record
  • Conventional Tailings

Similar projects

Goldstrike Mine

Engineer of Record Barrick’s Goldstrike Mine processes 30,000 tons of gold ore per day from its combined open-pit/underground operations located in the historic Carlin Trend in Nevada, U.S.A. Goldstrike’s tailings are stored in the North Block Tailings Disposal Facility (NBTDF).…

VIEW PROJECT

Anglo American Quellaveco Mine | PerĂº

Tierra Group supervised a geotechnical and hydrogeologic drilling investigation program at Anglo American’s Quellaveco Mine in the Moquegua Region of Peru. Geotechnical Investigation Tierra Group developed a geotechnical and hydrogeological research plan within and near the Quellaveco Pit footprint. This…

VIEW PROJECT

American Gypsum

American Gypsum Pit Planning and Support Tierra Group began working at American Gypsum’s Eagle-Gypsum mine located in Gypsum, Colorado in 2014 evaluating haul road improvements. A trade-off study provided a tool for American Gypsum to evaluate safety improvements including alternative haul road…

VIEW PROJECT

Don Mario Gold Mine

Don Mario Mine is an open pit gold/copper mine located in the Chiquitos Province, Santa Cruz, Bolivia that has been operating since 2002 and currently produces 2700 tpd mill throughput. Conventional tailings are transported and deposited in a high-density polyethylene lined geomembrane valley…

VIEW PROJECT

Jerritt Canyon Mine

2023 Dam Inspections/Review Tierra Group completed a site visit to inspect three tailings storage facilities (TSFs) and the Evaporation Pond. In addition to the site visit and dam inspections, design and monitoring reports (prepared by others) were reviewed for each…

VIEW PROJECT

Goldfield Bonanza Project

Lode-Star Gold, Inc., in advance of their proposed mining operations, submited a Physical Separation Facility application with the State of Nevada for their Goldfield Bonanza Project located in Esmeralda County, Nevada. The mine, located in the historic high-grade gold-bearing district of…

VIEW PROJECT

Sweetwater Mine

Sweetwater Mine Permitting Tierra Group’s Team began work at the Sweetwater mine in 1993 assisting permitting and developing tailings impoundment management strategies for the mine. We successfully designed and installed an innovative internal seal for repair of the mine’s damaged…

VIEW PROJECT

Dam Assessment

Tierra Group performed a site visit and visual inspection of a dam to assess its overall condition and provide the Owner recommendations for continued maintenance, monitoring, and improvements. The assessment was a follow-up to previous work completed by Tierra Group…

VIEW PROJECT

El Diamante Hydropower Dam

Tierra Group conducted a Preliminary Site Assessment of a potential large-scale landslide near the El Diamante Hydropower Complex in Matagalpa, Nicaragua.

VIEW PROJECT

Lagunas Norte Mine

The Lagunas Norte Mine, operated by Barrick Misquichilca S.A., is an open pit gold mine located in the Quiruvilca district, Santiago de Chuco province, La Libertad department, Perú. The main study objective was to evaluate the volume of effluent discharge…

VIEW PROJECT

Mt. Todd Dam Assessment

Tierra Group conducted an Independent Technical review of Vista Gold Corp’s Mt. Todd Tailings Storage Facility Expansion in Northern Territory, Australia. Tierra Group assisted the 2025 Mt. Todd feasibility study project providing TSF and waste rock dump design and water…

VIEW PROJECT

Tailings Review & Assurance Audit | Montana

Tailings Management Assurance Review Tierra Group served as the Lead Auditor and conducted MARs for the TSFs at this confidential project. Tierra Group reviewed all available facility documentation, including OMS Manuals, EAPs, design reports, As-Built Reports, annual inspection reports, and other…

VIEW PROJECT