Sweetwater Mine

Project Highlights:

  • Permitting
  • Tailings Operations Planning
  • CQA
  • Liquefaction
  • Seismic Stability
  • Slope Stability Analysis
  • Engineer of Record
  • Conventional Tailings

Sweetwater Mine Permitting

Tierra Group’s Team began work at the Sweetwater mine in 1993 assisting permitting and developing tailings impoundment management strategies for the mine. We successfully designed and installed an innovative internal seal for repair of the mine’s damaged decant discharge conduit. Tierra Group began working at Sweetwater again in 2015 designing a 5 foot TSF dam and spillway raise. Unique design challenges were overcome with a comprehensive field investigation including CPT and hollow stem auger drilling. Liquefaction analyses were performed and incorporated into the upstream raise design. A challenging hydrology model was completed and a raise to the existing spillway was designed. The raise design was approved by MDNR Dam and Reservoir Safety council in March 2016. Construction was completed in early 2017 with support provided with Tierra Group overseeing construction activities and evaluating proposed design changes. An As-Built report was completed in April 2017 conforming to MDNR requirements. Tierra Group provided additional support at Sweetwater by designing a 23 foot dam raise providing more than 15 years additional tailings capacity. A new spillway and saddle dam was included in the design. The dam raise design was approved by MDNR in July 2018. Tierra Group supported dam raise construction in 2021 completing design optimizations that reduced construction costs, supporting construction, and completing an as-built report.

Project Highlights:

  • Permitting
  • Tailings Operations Planning
  • CQA
  • Liquefaction
  • Seismic Stability
  • Slope Stability Analysis
  • Engineer of Record
  • Conventional Tailings

Similar projects

Karouni Mine

Tierra Group reviewed and provided pit slope recommendations and conducted hydrological assessments for the Resource 1 and 2 deposits water management system at Troy Resources’ Karouni Mine (Karouni). Advanced pre-feasibility level recommendations for pit development were provided based on benchmarking…

VIEW PROJECT

Hermosa Project

Tierra Group provided a Third-Party review of the Hermosa Project Tailings Storage Facility Design and Construction stages 1 & 2 in Patagonia, Arizona

VIEW PROJECT

Pierina Mine

Barrick Gold Corporation’s Pierina Mine in Ancash Department, Perú began operations in 1998. A progressive reclamation and closure plan began in 2013.  In 2015-16 Tierra Group developed detailed engineering designs for channels, sediment traps, two 45,000 m3 sediment ponds, water…

VIEW PROJECT

Douglas County Public Works

Tierra Group updated the County’s Standard Operating Procedures (SOPs) for Municipal Operations to maintain the County’s compliance with the requirements for stormwater discharges from the County’s municipal separate storm sewer system (MS4) under the Colorado Discharge Permit System (CDPS). Tierra…

VIEW PROJECT

Camino Rojo Heap Leach Design

Tierra Group provided a heap leach facility detailed design (for construction), procurement, CQA and project management for the Camino Rojo Mine in Zacatecas, Mexico.

VIEW PROJECT

Orotex Mine Project

Tierra Group provided tailings engineering design and consulting services for the redevelopment of the Orotex underground mine in Alajuela, Costa Rica. Tierra Group's areas of responsibility included tailings and water management in this environmentally sensitive, high rainfall, tropical, mountainous region.

VIEW PROJECT

El Mochito Mine

El Mochito is an underground zinc/silver mine located in the Santa Barbara Mountains in north-central Honduras. Tierra Group’s Team has been providing Tailings Stewardship Services at El Mochito continuously for the past 26 years. Since 1989, Tierra Group engineers have provided…

VIEW PROJECT

Quinsam Coal

Tierra Group served as an independent subject matter expert for the Quinsam Coal Corporation (QCC) Independent Tailings Review Board (ITRB) in British Columbia, Canada. The annual review process included review of existing documents, a site visit, and collaborative meetings with…

VIEW PROJECT

Big Ledge Mine

Tierra Group developed a water balance model to track flows into a backfilled pit at the closed Big Ledge Mine Barite Operation near Wells, Nevada. The Model was used to determine pipeline sizing to a remote treatment pond that is…

VIEW PROJECT

Stibnite Gold Project

The Stibnite project is located in the remote central Idaho Rockies near the town of Yellow Pine.  It is a brownfields gold-antimony project featuring three open pits and an anticipated 22,000 tpd plant throughput, along with challenging terrain and environmental…

VIEW PROJECT

Boleo Mine

Tierra Group performed an independent technical peer review of the Boleo Mine’s operating tailings storage facility design. In doing so Tierra Group identified several design modifications that when implemented for future stages will reduce sustaining capital cost expenditures by several…

VIEW PROJECT

Yauricocha Mine

The Yauricocha Mine is a polymetallic (copper, lead, zinc) underground mine located in Yauyos Province, Lima, Peru. Tailings are deposited in the Yauricocha Tailings Storage Facility (TSF) located 3km from the process plant. Tierra Group was engaged in 2015 to…

VIEW PROJECT