La Negra Mine

Project Highlights:

  • Tailings Storage Safety Audit

Tierra Group performed a tailings storage facility safety (TSF) audit for the 90 m high upstream constructed tailings dam at La Negra Mine in Querétaro, Mexico. The project included a TSF dam inspection and Dam Safety Inspection Report (DSIR) containing operational and Best Management Practice (BMP) improvement recommendations.

Project Highlights:

  • Tailings Storage Safety Audit

Similar projects

Myra Falls

Tierra Group provides Tailings Stewardship Services for Nyrstar's Myra Falls Mine Tailings Storage Facility. Tierra Group performed a 5-year Dam Safety Review consistent with the Canadian Dam Association protocols, site training and in depth inspections of management practices and facilities…

VIEW PROJECT

Bald Mountain Mine

Tierra Group assisted the Bald Mountain Mine Project Development Team with an evaluation of potential uses for spent ore on legacy heap leach facilities. Tierra Group completed a collaborative trade-off study with site personnel evaluating spent ore use as overliner…

VIEW PROJECT

Goldfield Bonanza Project

Lode-Star Gold, Inc., in advance of their proposed mining operations, submited a Physical Separation Facility application with the State of Nevada for their Goldfield Bonanza Project located in Esmeralda County, Nevada. The mine, located in the historic high-grade gold-bearing district of…

VIEW PROJECT

2020 TSF Annual Dam Inspection

Tierra Group completed an annual dam safety inspection (DSI) to meet both Nevada Division of Water Resources (NDWR) Dam Safety and the client's requirements. The DSI included reviewing monitoring data, a dam and appurtenant structures inspection, and a DSI report.

VIEW PROJECT

Bolivar Mine

The Bolivar mine is a 3,000 tonne per day underground mining operation in Chihuahua, Mexico producing copper, zinc, silver, and gold. Space constraints in mountainous terrain require dewatering tailings to reduce required area for tailings storage. Tierra Group is assisting…

VIEW PROJECT

Contonga Mine

Contonga, a 990 tpd underground Zinc mine located in Perú’s Ancash Region, has been in operation for more than 25 years. Tierra Group team members assisted Nyrstar’s acquisition due diligence team by performing a fatal flaw analysis of Contonga’s Tucush…

VIEW PROJECT

Newcrest Red Chris Tailings Stewardship

Tierra Group provided Tailings Stewardship Services for TSFs and water dams at the Cadia, Terfer, and Red Chris properties. Responsibilities included data/report review; identifying and assisting the client with managing risks, liabilities, controls, and reporting; evaluating progress towards GISTM compliance;…

VIEW PROJECT

Los Filos Mine

Tierra Group was selected to assist Goldcorp with global Tailings Stewardship Strategy (TSS) implementation at all of Goldcorp’s active tailings sites in Latin America (Mexico, Argentina, and Guatemala). Tierra Group worked in conjunction with Goldcorp and another global engineering consulting…

VIEW PROJECT

Rosario Mine

Tierra Group performed a Dam Safety Review (DSR) including geotechnical investigations and seepage and slope stability analyses for a 20-m high TSF at this 300‑tpd underground polymetallic mine. The audit was prepared following the Mt. Polley tailings dam failure in…

VIEW PROJECT

Don Mario Gold Mine

Don Mario Mine is an open pit gold/copper mine located in the Chiquitos Province, Santa Cruz, Bolivia that has been operating since 2002 and currently produces 2700 tpd mill throughput. Conventional tailings are transported and deposited in a high-density polyethylene lined geomembrane valley…

VIEW PROJECT

Los Gatos Project

TSF Design and CQA Tierra Group provided detailed Stage 1 and 2 Tailings Storage Facility design, conducted a process plant geotechnical foundation investigation, and provided Construction Quality Assurance for Sunshine Silver Mining's Los Gatos Project in Chihuahua, Mexico. Tierra Group then…

VIEW PROJECT

San Bartolome Mine | NI 43-101 Tailings Technical Review & Report

Tierra Group performed an Independent Tailings Technical Review to support the San Bartolomé Mine Prefeasibility Study (PFS) NI 43-101 Technical Report (TR). SRK Consulting Inc. (SRK) is the primary TR author. Tierra Group will provided a Qualified Person (QP) to oversee…

VIEW PROJECT