Tierra Group performed the La Caridad TSF Audit. Tierra Group’s scope of work entailed a site visit, data review, dam safety inspection (DSI), site interviews, and provided best management practices training for operations personnel.
Topia Mine Phases 1-3Tierra Group supervised the first 3 phases of Geologic Mapping and Instrumentation Installation and developed a Mechanically Stabilized Earth Wall Design at Great Panther Silver’s Topia Mine in Durango, Mexico.
Tailings Storage Facility & Engineer of Record (2012-present) Tierra Group engineers provided engineering consultancy, design, and construction services for three Tailings Storage Facilities (TSF) (Santa Rosa, Santa Rosa West, and San José) to facilitate 20 years of uninterrupted mine operations. Tierra…
East Boulder Tailings Independent Review Panel (2018-present) Tierra Group reviewed a TSF design to support an NI 43-101 compliant Feasibility Study. The TSF design incorporated a paste tailings disposal method in an environmentally sensitive fisheries habitat. Tierra Group sits on the Independent…
Tierra Group performed the La Caridad TSF Audit. Tierra Group’s scope of work entailed a site visit, data review, dam safety inspection (DSI), site interviews, and provided best management practices training for operations personnel.
Tierra Group was commissioned by Doe Run to design a new tailings storage facility at the Brushy Creek Mine. Tierra Group completed a geotechnical investigation including boring, classifying, and sampling soil and rock. Trade-off studies were performed to minimize construction…
Glencore’s Antapaccay mine is located in the Espinar province, Cuzco, Perú. Tierra Group logged geotechnical, geological and geo-mechanical properties of drill core advanced in Antapaccay's Northern Pit. Approximately 6,000 meters of core were logged. Specific samples were selected for geotechnical…
Jaguar's gold operations, Turmalina, Paciência and Caeté, are located in the Iron Quadrangle region, a prolific greenstone belt near the city of Belo Horizonte in the state of Minas Gerais, Brazil. Jaguar controls 27,357 hectares of mineral concessions in this…
Tierra Group provided slope stability analysis for Agnico Eagle’s dry stack tailings storage facility containing 330,000 tonnes of tailings.
Hollister Waste Rock Facility Storage Tierra Group performed a third-party peer review of a Waste Rock Storage Facility (WRSF) design at Klondex Mines’ (Klondex) Hollister Mine in northern Nevada. The WRSF, as designed, involved lining the mine’s existing West Pit…
Tierra Group provides Tailings Stewardship Services for the Marlin Mine Tailings Storage Facility. Tierra Group performed a 5-year Dam Safety Review consistent with the Canadian Dam Association protocols, a Facilitated Risk Assessment, site training and in depth inspections of management…
Midas Gold’s project is located in the remote central Idaho Rockies near the town of Yellow Pine. It is a brownfields gold-antimony project featuring three open pits and an anticipated 22,000 tpd plant throughput, along with challenging terrain and environmental…
Tierra Group provided a Third-Party review of the Hermosa Project Tailings Storage Facility Design and Construction stages 1 & 2 in Patagonia, Arizona
Topia Mine Phases 1-3Tierra Group supervised the first 3 phases of Geologic Mapping and Instrumentation Installation and developed a Mechanically Stabilized Earth Wall Design at Great Panther Silver’s Topia Mine in Durango, Mexico.
Tailings Storage Facility & Engineer of Record (2012-present) Tierra Group engineers provided engineering consultancy, design, and construction services for three Tailings Storage Facilities (TSF) (Santa Rosa, Santa Rosa West, and San José) to facilitate 20 years of uninterrupted mine operations. Tierra…
East Boulder Tailings Independent Review Panel (2018-present) Tierra Group reviewed a TSF design to support an NI 43-101 compliant Feasibility Study. The TSF design incorporated a paste tailings disposal method in an environmentally sensitive fisheries habitat. Tierra Group sits on the Independent…
Tierra Group performed the La Caridad TSF Audit. Tierra Group’s scope of work entailed a site visit, data review, dam safety inspection (DSI), site interviews, and provided best management practices training for operations personnel.
Tierra Group was commissioned by Doe Run to design a new tailings storage facility at the Brushy Creek Mine. Tierra Group completed a geotechnical investigation including boring, classifying, and sampling soil and rock. Trade-off studies were performed to minimize construction…
Glencore’s Antapaccay mine is located in the Espinar province, Cuzco, Perú. Tierra Group logged geotechnical, geological and geo-mechanical properties of drill core advanced in Antapaccay's Northern Pit. Approximately 6,000 meters of core were logged. Specific samples were selected for geotechnical…
Jaguar's gold operations, Turmalina, Paciência and Caeté, are located in the Iron Quadrangle region, a prolific greenstone belt near the city of Belo Horizonte in the state of Minas Gerais, Brazil. Jaguar controls 27,357 hectares of mineral concessions in this…
Tierra Group provided slope stability analysis for Agnico Eagle’s dry stack tailings storage facility containing 330,000 tonnes of tailings.
Hollister Waste Rock Facility Storage Tierra Group performed a third-party peer review of a Waste Rock Storage Facility (WRSF) design at Klondex Mines’ (Klondex) Hollister Mine in northern Nevada. The WRSF, as designed, involved lining the mine’s existing West Pit…
Tierra Group provides Tailings Stewardship Services for the Marlin Mine Tailings Storage Facility. Tierra Group performed a 5-year Dam Safety Review consistent with the Canadian Dam Association protocols, a Facilitated Risk Assessment, site training and in depth inspections of management…
Midas Gold’s project is located in the remote central Idaho Rockies near the town of Yellow Pine. It is a brownfields gold-antimony project featuring three open pits and an anticipated 22,000 tpd plant throughput, along with challenging terrain and environmental…
Tierra Group provided a Third-Party review of the Hermosa Project Tailings Storage Facility Design and Construction stages 1 & 2 in Patagonia, Arizona
Topia Mine Phases 1-3Tierra Group supervised the first 3 phases of Geologic Mapping and Instrumentation Installation and developed a Mechanically Stabilized Earth Wall Design at Great Panther Silver’s Topia Mine in Durango, Mexico.