Midas Mine

Project Highlights:

  • Tailings Management Plan
  • Facility Water Balance
  • Tailings Facility Siting Analysis

The Midas Mine is located in northern Nevada, and is owned and operated by Hecla Mining Company.  The mine is an underground mine with an operating mill. The mine’s existing tailings facilities are nearing their end of operating life and the mine was investigating ways to maximize storage within each facility. Tierra Group assisted Hecla by preparing several evaluations to aid in the mine’s tailings storage operations. Tierra Group’s evaluation included preparation of a tailings management plan and a facility water balance. These evaluations provided the mine with information to manage their tailings deposition and supernatant water pools while also maximizing the facility’s storage capacity. Additionally, Tierra Group prepared a siting study to determine the preferred location of a future tailings storage facility. The siting study included preparing the feasibility level facility design at multiple sites and preparing a design report with Tierra Group’s recommendations.

Project Highlights:

  • Tailings Management Plan
  • Facility Water Balance
  • Tailings Facility Siting Analysis

Similar projects

Brushy Creek

Tierra Group provided a raise design for Doe Run's Brushy Creek tailings embankment, a facility first commissioned in 1973. Cone penetration testing, liquefaction analysis, seepage modeling, and slope stability modeling were performed for the embankment. Hydrology, spillway design, and impoundment layout…

VIEW PROJECT

Masbate Mine

Tierra Group performed a study of Masbate’s 12-Mt tailings storage facility. Services provided included a forensic study to determine the cause of seepage through an abutment and performed an independent safety audit of tailings management practices. A risk analysis was performed…

VIEW PROJECT

Newcrest Cadia Tailings Stewardship

Tierra Group provided Tailings Stewardship Services for TSFs and water dams at the Cadia, Terfer, and Red Chris properties. Responsibilities included data/report review; identifying and assisting the client with managing risks, liabilities, controls, and reporting; evaluating progress towards GISTM compliance;…

VIEW PROJECT

El Diamante Hydropower Dam

Tierra Group conducted a Preliminary Site Assessment of a potential large-scale landslide near the El Diamante Hydropower Complex in Matagalpa, Nicaragua.

VIEW PROJECT

Morelos Mine

Tierra Group designed and implemented a stability and safety monitoring plan for Torex Gold’s Morelos Mine dry stack tailings storage facility (TSF). The monitoring plan includes installing inclinometers and vibrating wire piezometers, and training operations staff to download instrumentation readings.…

VIEW PROJECT

Orotex Mine Project

Tierra Group provided tailings engineering design and consulting services for the redevelopment of the Orotex underground mine in Alajuela, Costa Rica. Tierra Group's areas of responsibility included tailings and water management in this environmentally sensitive, high rainfall, tropical, mountainous region.

VIEW PROJECT

Hayden Operations

Tierra Group implemented a corporate Tailings Stewardship Strategy (TSS) at all of ASARCO Grupo Mexico’s mines in Arizona, USA (Hayden, Mission and Ray mines). Tierra Group conducted a site visit to each site to perform dam safety inspections, interview operations staff,…

VIEW PROJECT

San Francisco Mine

Tierra Group conducted geo-electrical testing to locate leaks present in the geomembrane liners underlying a Solution Conveyance Canal, Sumps 1 and 2, and the Intermediate Pond at Timmins Gold Corp’s San Francisco Mine in Sonora, Mexico. Leak detection testing procedures…

VIEW PROJECT

Esmeralda Mill

Tierra Group was contracted by Waterton Global Mining Company to prepare the FPCP for TSF No.1 at the Esmeralda Mine. TSF No.1 covered approximately 100 acres, included a rockfill embankment with a maximum height approximately 60 feet, and stored gold tailings. Work…

VIEW PROJECT

Bald Mountain Mine

Tierra Group assisted the Bald Mountain Mine Project Development Team with an evaluation of potential uses for spent ore on legacy heap leach facilities. Tierra Group completed a collaborative trade-off study with site personnel evaluating spent ore use as overliner…

VIEW PROJECT

El Limón Mine

Tailings Storage Facility & Engineer of Record (2012-present) Tierra Group engineers provided engineering consultancy, design, and construction services for three Tailings Storage Facilities (TSF) (Santa Rosa, Santa Rosa West, and San José) to facilitate 20 years of uninterrupted mine operations. Tierra…

VIEW PROJECT

Boleo Mine

Tierra Group performed an independent technical peer review of the Boleo Mine’s operating tailings storage facility design. In doing so Tierra Group identified several design modifications that when implemented for future stages will reduce sustaining capital cost expenditures by several…

VIEW PROJECT