Çöpler Tailings Storage Facility and Heap Leach Facility Technical Review

Project Highlights:

  • Dam Safety Review
  • Technical Review
  • Heap Leach
  • Conventional Tailings
  • Earthfill Dam
  • Downstream Dam

Tierra Group has a history of annually providing third-party technical reviews for the tailings storage facility and heap leach facility at Anagold's Çöpler Gold Mine in Middle Anatolia, Turkey.

Additionally, Tierra Group currently performs independent technical reviews for the rockfill tailings dam and heap leach facility on an annual basis.

Project Highlights:

  • Dam Safety Review
  • Technical Review
  • Heap Leach
  • Conventional Tailings
  • Earthfill Dam
  • Downstream Dam

Similar projects

Hollister Waste Rock Facility

Hollister Waste Rock Facility Storage Tierra Group performed a third-party peer review of a Waste Rock Storage Facility (WRSF) design at Klondex Mines’ (Klondex) Hollister Mine in northern Nevada. The WRSF, as designed, involved lining the mine’s existing West Pit…

VIEW PROJECT

Brushy Creek

Tierra Group provided a raise design for Doe Run's Brushy Creek tailings embankment, a facility first commissioned in 1973. Cone penetration testing, liquefaction analysis, seepage modeling, and slope stability modeling were performed for the embankment. Hydrology, spillway design, and impoundment layout…

VIEW PROJECT

Pirquitas Tailings Review

Tierra Group prepared a civil engineering design for SSR Mining’s Mina Pirquitas in Jujuy Province, Argentina and developed current and future water-mass balance through hydrological/hydraulics calculations and modeling. Tierra Group developed the ultimate tailings surface, deposition plan, spillway relocation analysis,…

VIEW PROJECT

2020 TSF Annual Dam Inspection

Tierra Group completed an annual dam safety inspection (DSI) to meet both Nevada Division of Water Resources (NDWR) Dam Safety and the client's requirements. The DSI included reviewing monitoring data, a dam and appurtenant structures inspection, and a DSI report.

VIEW PROJECT

Aranzazú Mine

The Aranzazú Mine is a copper-gold-silver mine located in the northeastern region of Zacatecas, Mexico. The mine includes both open pit and underground operations. The mill currently processes 2,600 tonnes of ore per day. Tierra Group finalized the geotechnical investigation…

VIEW PROJECT

Tennessee Mines

Tierra Group performed Dam Safety Reviews (DSRs) for Nyrstar’s tailings storage facilities (TSFs) located in Tennessee, United States.  Tierra Group served as the Tailings Reviewer to ensure conformity with local regulations, the Nyrstar Tailings Storage Facility (TSF) Standard, and to…

VIEW PROJECT

El Limón Mine

Tailings Storage Facility & Engineer of Record (2012-present) Tierra Group engineers provided engineering consultancy, design, and construction services for three Tailings Storage Facilities (TSF) (Santa Rosa, Santa Rosa West, and San José) to facilitate 20 years of uninterrupted mine operations. Tierra…

VIEW PROJECT

Caeté Complex

Tierra Group developed a site-wide water management plan, and performed a liquefaction potential study following the Samarco tailings dam failure in Minas Gerais, Brazil. A tailings storage facility water balance was developed to optimize water usage and minimize risks at…

VIEW PROJECT

North Mara Mine | Tailings Assurance Audit

Tierra Group completed a TAA for the North Mara Tailings Storage Facility (TSF). The TAA was completed to ensure the TSF and site operations complied with Barrick’s Tailings Management Standard, which closely mirrors the Global Industry Standard on Tailings Management (GISTM)…

VIEW PROJECT

Hermosa Project

Tierra Group provided a Third-Party review of the Hermosa Project Tailings Storage Facility Design and Construction stages 1 & 2 in Patagonia, Arizona

VIEW PROJECT

Camino Rojo Heap Leach Design

Tierra Group provided a heap leach facility detailed design (for construction), procurement, CQA and project management for the Camino Rojo Mine in Zacatecas, Mexico.

VIEW PROJECT

Pitarrilla Mine

Tierra Group participated as a member of a multi-disciplinary project team to develop a Definitive Feasibility study for a 16,000 tpd silver mine in Durango, Mexico. Tierra Group's responsibilities included designing a 112 Mt tailings storage facility, developing a site-wide…

VIEW PROJECT