El Limón Mine

Project Highlights:

  • MSE Dam Raise
  • TSF Design
  • Water Balance
  • Operations Plans
  • Rock-Fill Conventional TSF Design
  • PMF Hydrology and Hydraulics Designs
  • Facility Expansion
  • Tailings Coverage
  • Seismic Stability
  • Site-Wide Mine Closure & Reclamation Plan
  • Aquifer Testing
  • Independent Design Review
  • Geotechnical Investigation
  • Pre-Feasibility Study
  • Construction Quality Assurance

Tailings Storage Facility & Engineer of Record (2012-present)

Tierra Group engineers provided engineering consultancy, design, and construction services for three Tailings Storage Facilities (TSF) (Santa Rosa, Santa Rosa West, and San José) to facilitate 20 years of uninterrupted mine operations. Tierra Group’s services spanned the full tailings lifecycle including siting studies, environmental impact assessments, permitting, feasibility through detailed engineering design, bid documents, resident engineering, construction quality assurance, operations and maintenance, decommissioning, closure, and reclamation.

Tierra Group served as the Engineer of Record (EoR) for the Santa Rosa, Santa Rosa West, and San José TSFs. As the EoR, Tierra Group developed detailed TSF water balance spreadsheet tools, reviewed monitoring data collected by B2Gold and later Calibre each month, conducted annual TSF inspections, and prepared an annual monitoring report to document TSF performance and dam safety.

Aquifer Testing

Tierra Group performed a comprehensive pumping test data review of the mine's revised dewatering plan, with inflows up to 3,000 gpm.

Independent Design Review

Tierra Group performed an independent design review of an open pit design and provided design improvement recommendations.

Stability Evaluation

Tierra Group performed a geotechnical field investigation to support the San Jose TSF Stage 4 final design and evaluate pit slope stability. Tierra Group incorporated field data into a 3D geologic/geotechnical model that evaluated pit slope stability.

Pit Feasibility Investigation

Tierra Group conducted a geotechnical field investigation to characterize the geology and determine preliminary pit slopes for three new pits. Pit slope angles were used to support the feasibility pit design (performed by others).

Pit Feasibility Investigation

Tierra Group provided CQA services (earthworks, geomembrane, and geotechnical monitoring instrumentation) for the San Jose Tailings Storage Facility (TSF) Phase 4B expansion.

Project Highlights:

  • MSE Dam Raise
  • TSF Design
  • Water Balance
  • Operations Plans
  • Rock-Fill Conventional TSF Design
  • PMF Hydrology and Hydraulics Designs
  • Facility Expansion
  • Tailings Coverage
  • Seismic Stability
  • Site-Wide Mine Closure & Reclamation Plan
  • Aquifer Testing
  • Independent Design Review
  • Geotechnical Investigation
  • Pre-Feasibility Study
  • Construction Quality Assurance

Similar projects

Lagunas Norte Mine

The Lagunas Norte Mine, operated by Barrick Misquichilca S.A., is an open pit gold mine located in the Quiruvilca district, Santiago de Chuco province, La Libertad department, Perú. The main study objective was to evaluate the volume of effluent discharge…

VIEW PROJECT

Bald Mountain Mine

Tierra Group assisted the Bald Mountain Mine Project Development Team with an evaluation of potential uses for spent ore on legacy heap leach facilities. Tierra Group completed a collaborative trade-off study with site personnel evaluating spent ore use as overliner…

VIEW PROJECT

El Diamante Hydropower Dam

Tierra Group conducted a Preliminary Site Assessment of a potential large-scale landslide near the El Diamante Hydropower Complex in Matagalpa, Nicaragua.

VIEW PROJECT

Marlin Mine

Tierra Group provides Tailings Stewardship Services for the Marlin Mine Tailings Storage Facility. Tierra Group performed a 5-year Dam Safety Review consistent with the Canadian Dam Association protocols, a Facilitated Risk Assessment, site training and in depth inspections of management…

VIEW PROJECT

Lost Creek Project | USA

Tierra Group is assisting Millcreek Mining and Black Mountain Sand with the preparation of permitting documents for the Lost Creek Project; including a preliminary Stormwater Management Plan, preliminary Groundwater Monitoring Plan, and general permitting exhibits. Tierra Group conducted a site geotechnical…

VIEW PROJECT

Bunker Hill | Tailings Storage Facility (TSF) Design

Tierra Group designed the Bunker Hill dry stack TSF. The TSF design was challenging given the limited land area, steep terrain, seasonal cold weather, and surface water management. Tierra Group’s scope of work included siting the facilities, geotechnical investigations, civil…

VIEW PROJECT

Stibnite Gold Project

The Stibnite project is located in the remote central Idaho Rockies near the town of Yellow Pine.  It is a brownfields gold-antimony project featuring three open pits and an anticipated 22,000 tpd plant throughput, along with challenging terrain and environmental…

VIEW PROJECT

Pinos Altos Mine

Tierra Group provided slope stability analysis for Agnico Eagle’s dry stack tailings storage facility containing 330,000 tonnes of tailings.

VIEW PROJECT

Bunker Hill

Dry Stack Tailings Storage Facility Tierra Group designed a dry stack TSF to store excess tailings from the underground paste backfill. The dry stack TSF was challenging, given the limited land area, steep terrain, seasonal cold weather, and surface water…

VIEW PROJECT

NioCorp’s Elk Creek | Tailings Storage Facility (TSF) Feasibility Study

Tierra Group advanced the TSF design to a Feasibility Level according to the Canadian National Instrument NI 43-101 and the U.S. Security and Exchange Commission’s Subpart SK-1300 regulation. Tierra Group’s scope of work included a geotechnical investigation, engineering analysis, and TSF…

VIEW PROJECT

Newcrest Red Chris Tailings Stewardship

Tierra Group provided Tailings Stewardship Services for TSFs and water dams at the Cadia, Terfer, and Red Chris properties. Responsibilities included data/report review; identifying and assisting the client with managing risks, liabilities, controls, and reporting; evaluating progress towards GISTM compliance;…

VIEW PROJECT

San Francisco Mine

Tierra Group conducted geo-electrical testing to locate leaks present in the geomembrane liners underlying a Solution Conveyance Canal, Sumps 1 and 2, and the Intermediate Pond at Timmins Gold Corp’s San Francisco Mine in Sonora, Mexico. Leak detection testing procedures…

VIEW PROJECT