Tierra Group conducted a Preliminary Site Assessment of a potential large-scale landslide near the El Diamante Hydropower Complex in Matagalpa, Nicaragua.
Tierra Group has a history of annually providing third-party technical reviews for the tailings storage facility and heap leach facility at Anagold's Çöpler Gold Mine in Middle Anatolia, Turkey. Additionally, Tierra Group currently performs independent technical reviews for the rockfill…
Lode-Star Gold, Inc., in advance of their proposed mining operations, submited a Physical Separation Facility application with the State of Nevada for their Goldfield Bonanza Project located in Esmeralda County, Nevada. The mine, located in the historic high-grade gold-bearing district of…
Tierra Group completed a siting study to evaluate six potential sites for a paste TSF. Tierra Group prepared civil layouts for each TSF, determining embankment fill volumes, evaluating required diversions for upstream catchment areas, and pipeline corridor layouts. Tierra Group…
Tierra Group assisted the Bald Mountain Mine Project Development Team with an evaluation of potential uses for spent ore on legacy heap leach facilities. Tierra Group completed a collaborative trade-off study with site personnel evaluating spent ore use as overliner…
Tierra Group completed a Tailings Assurance Audit (TAA) for a closed Tailings Storage Facility (TSF). The TAA was completed to ensure the TSF and site operations complied with the Company's Tailings Management Standard, which closely mirrors Global Industry Standard on…
TSF Design and CQA Tierra Group provided detailed Stage 1 and 2 Tailings Storage Facility design, conducted a process plant geotechnical foundation investigation, and provided Construction Quality Assurance for Sunshine Silver Mining's Los Gatos Project in Chihuahua, Mexico. Tierra Group then…
Tierra Group performed a tailings storage facility safety (TSF) audit for the 90 m high upstream constructed tailings dam at La Negra Mine in Querétaro, Mexico. The project included a TSF dam inspection and Dam Safety Inspection Report (DSIR) containing operational…
Tierra Group provided Tailings Stewardship Services including a dam inspection, slope stability analysis review and operational improvements for Endeavour Silver’s El Cubo tailings storage facility in Guanajuato, Mexico.
Tierra Group participated as a member of a multi-disciplinary project team to develop a Definitive Feasibility study for a 16,000 tpd silver mine in Durango, Mexico. Tierra Group's responsibilities included designing a 112 Mt tailings storage facility, developing a site-wide…
Tierra Group performed an independent engineering design review of a Cemented Tailings Facility (CTF) and multiple processes and freshwater ponds. Tailings will be mixed with cement at the paste plant and deposited in the CTF along with underground mine development…
Tierra Group was commissioned by Doe Run to design a new tailings storage facility at the Brushy Creek Mine. Tierra Group completed a geotechnical investigation including boring, classifying, and sampling soil and rock. Trade-off studies were performed to minimize construction…
Tierra Group provided Tailings Stewardship Services for TSFs and water dams at the Cadia, Terfer, and Red Chris properties. Responsibilities included data/report review; identifying and assisting the client with managing risks, liabilities, controls, and reporting; evaluating progress towards GISTM compliance;…