El Gallo Mine

Project Highlights:

  • Heap Leach Pad Expansion Design
  • Solution Collection System Design
  • Detailed Design for Construction
  • As-Built Drawing(s) and Report
  • Slope Stability
  • Grading Plan
  • Construction Support
  • Pipe Crushing Analysis
  • Stacking Plan

El Gallo is a 3,000 tpd open-pit gold/silver mine located in the foothills of the Sierra Madre Mountain Range in Mexico’s Sinaloa State. Gold is recovered through heap leaching and adsorption/desorption/recovery (ADR). Production commenced at El Gallo with the first gold pour in September 2012. Tierra Group’s design team designed a heap leach pad expansion during the first half of 2012 as part of the re-commissioning of the El Gallo project. In addition, Tierra Group developed construction documents (drawings and construction specifications) and provided engineering support during construction.

Project Highlights:

  • Heap Leach Pad Expansion Design
  • Solution Collection System Design
  • Detailed Design for Construction
  • As-Built Drawing(s) and Report
  • Slope Stability
  • Grading Plan
  • Construction Support
  • Pipe Crushing Analysis
  • Stacking Plan

Similar projects

Empire State Mine

Dam Breach Analyses Tierra Group prepared a DBA to evaluate potential downstream impacts due to a hypothetical failure (breach) in three components of Empire State Mines (ESM) tailings storage facility (TSF): North Dam (ND), South Dam (SD), and West Perimeter…

VIEW PROJECT

El Cubo

Tierra Group provided Tailings Stewardship Services including a dam inspection, slope stability analysis review and operational improvements for Endeavour Silver’s El Cubo tailings storage facility in Guanajuato, Mexico.

VIEW PROJECT

Masbate Mine

Tierra Group performed a study of Masbate’s 12-Mt tailings storage facility. Services provided included a forensic study to determine the cause of seepage through an abutment and performed an independent safety audit of tailings management practices. A risk analysis was performed…

VIEW PROJECT

San Andrés Mine

Previous to Tierra Group, our Team performed a geotechnical forensics assessment, which determined that spent ore from an on-off leach pad operation had liquefied causing a debris flow, which threatened inundating a major river basin. A preventative detention buttress was…

VIEW PROJECT

Camino Rojo Heap Leach Design

Tierra Group provided a heap leach facility detailed design (for construction), procurement, CQA and project management for the Camino Rojo Mine in Zacatecas, Mexico.

VIEW PROJECT

New Jersey Mill TSF Scoping Study

Tierra Group completed the design for two 3-meter upstream raises to an existing paste tailings storage facility at New Jersey Mining Company’s New Jersey Mill site near Kellogg, Idaho. Work included performing a cone penetration testing (CPT) investigation of the…

VIEW PROJECT

Pierina Mine

Barrick Gold Corporation’s Pierina Mine in Ancash Department, Perú began operations in 1998. A progressive reclamation and closure plan began in 2013.  In 2015-16 Tierra Group developed detailed engineering designs for channels, sediment traps, two 45,000 m3 sediment ponds, water…

VIEW PROJECT

Equity Silver ITRB

Tierra Group's Matt Fuller, LEG, P.Geo. serves as one of three ITRB technical experts providing technical assurance of the Engineer of Record’s design and monitoring compliance with BC regulations, the Newmont Corporate Tailings Standard, and industry best practices.

VIEW PROJECT

Bunker Hill | Tailings Storage Facility (TSF) Design

Tierra Group designed the Bunker Hill dry stack TSF. The TSF design was challenging given the limited land area, steep terrain, seasonal cold weather, and surface water management. Tierra Group’s scope of work included siting the facilities, geotechnical investigations, civil…

VIEW PROJECT

Cove Project RIB Geotechnical Investigation

Tierra Group supported proposed Rapid Infiltration Basins Geotechnical Investigation at Au-reka Gold Corporation’s Cove Project in Nevada. Investigation included borehole drilling, test pits, infiltration testing and permeability testing.

VIEW PROJECT

Lost Creek Project | USA

Tierra Group is assisting Millcreek Mining and Black Mountain Sand with the preparation of permitting documents for the Lost Creek Project; including a preliminary Stormwater Management Plan, preliminary Groundwater Monitoring Plan, and general permitting exhibits. Tierra Group conducted a site geotechnical…

VIEW PROJECT

Tennessee Mines

Tierra Group performed Dam Safety Reviews (DSRs) for Nyrstar’s tailings storage facilities (TSFs) located in Tennessee, United States.  Tierra Group served as the Tailings Reviewer to ensure conformity with local regulations, the Nyrstar Tailings Storage Facility (TSF) Standard, and to…

VIEW PROJECT