Tierra Group's Matt Fuller, LEG, P.Geo. serves as one of three ITRB technical experts providing technical assurance of the Engineer of Record’s design and monitoring compliance with BC regulations, the Newmont Corporate Tailings Standard, and industry best practices.
El Gallo is a 3,000 tpd open-pit gold/silver mine located in the foothills of the Sierra Madre Mountain Range in Mexico’s Sinaloa State. Gold is recovered through heap leaching and adsorption/desorption/recovery (ADR). Production commenced at El Gallo with the first gold pour in September…
Tierra Group evaluated the Tajo Crimea Pit’s geotechnical and hydrogeological characteristics to determine in-pit tailings storage feasibility. The project scope defined geotechnical and hydrogeologic site conditions through field investigations and in-situ pump testing. Tierra Group developed a 3D groundwater model…
The Stibnite project is located in the remote central Idaho Rockies near the town of Yellow Pine. It is a brownfields gold-antimony project featuring three open pits and an anticipated 22,000 tpd plant throughput, along with challenging terrain and environmental…
Tierra Group began work at La Trinidad providing heap leach pad construction recommendations and a water balance. Tierra Group continued support with a heap leach pad expansion design, slope stability analyses, hydrologic analyses, diversion design, liner design, and leach solution…
Tierra Group performed an independent technical peer review of the Boleo Mine’s operating tailings storage facility design. In doing so Tierra Group identified several design modifications that when implemented for future stages will reduce sustaining capital cost expenditures by several…
Serving on Newmont Goldcorp’s Tailings Independent Review Board, Tierra Group provided an Independent Dam Safety Review for the Dona Lake Mine tailings storage facility in Pickle Lake, Ontario, Canada.
Tierra Group provided a raise design for Doe Run's Brushy Creek tailings embankment, a facility first commissioned in 1973. Cone penetration testing, liquefaction analysis, seepage modeling, and slope stability modeling were performed for the embankment. Hydrology, spillway design, and impoundment layout…
Heap Leach Procurement & Construction Quality Assurance Tierra Group provided Issued for Construction (IFC) design drawings and specifications for procurement requirements for the expansion of the Camino Rojo HLF. Information required included liner specifications, drainage collection piping, and quantities. Additionally,…
Tailings Management Assurance Review Tierra Group served as the Lead Auditor and conducted MARs for the TSFs at this confidential project. Tierra Group reviewed all available facility documentation, including OMS Manuals, EAPs, design reports, As-Built Reports, annual inspection reports, and other…
Tierra Group performed a technical peer review of the Isabella Pearl heap leach facility (HLF) owned by Gold Resource Corporation. Isabella Pearl mine is located at the west end of the Santa Fe mining district in the Walker Lane gold…
The Bolivar mine is a 3,000 tonne per day underground mining operation in Chihuahua, Mexico producing copper, zinc, silver, and gold. Space constraints in mountainous terrain require dewatering tailings to reduce required area for tailings storage. Tierra Group is assisting…
Tierra Group served as an independent subject matter expert for the Quinsam Coal Corporation (QCC) Independent Tailings Review Board (ITRB) in British Columbia, Canada. The annual review process included review of existing documents, a site visit, and collaborative meetings with…