Robinson Mine

Project Highlights:

  • Tailings Storage Facility
  • Trade-off Studies
  • Third-Party Review

Robinson Mine Tailings Impoundment Audit

Prior to joining Tierra Group, our Team completed a third-party tailings impoundment audit. The audit included reviewing operational procedures, monitoring, design, and future tailings storage planning. Produced an audit report for company’s internal use. (Tetra Tech, 2008)

Trade-off Studies

Tierra Group completed a trade-off study to evaluate raising the existing Tailings Storage Facility (TSF) or building a new TSF. An Alternatives Decision Matrix (ADM) was developed using weighted qualitative and quantitative parameters to evaluate the two options. A site visit was conducted to understand operational practices and challenges informing ADM development. Tierra Group worked collaboratively with the tailings operations and environmental teams ensuring TSF expansion option evaluations included institutional knowledge from “boots on the ground” team members.

2022 TSF Expansion Design Review

Tierra Group reviewed a TSF expansion design prepared by others. The third-party review aims to ensure conformance with the Nevada Division of Water Resources (NDWR) and Nevada Division of Environmental Protection (NDEP) regulations and industry best practices for tailings dam design. The design included a centerline raise of an existing cyclone sand embankment, raises to existing earthen embankments, and expansion of a geosynthetic-lined water retention area (Barge Operating Channel).

Project Highlights:

  • Tailings Storage Facility
  • Trade-off Studies
  • Third-Party Review

Similar projects

Equity Silver ITRB

Tierra Group's Matt Fuller, LEG, P.Geo. serves as one of three ITRB technical experts providing technical assurance of the Engineer of Record’s design and monitoring compliance with BC regulations, the Newmont Corporate Tailings Standard, and industry best practices.

VIEW PROJECT

Jaguar Mines

Jaguar's gold operations, Turmalina, Paciência and Caeté, are located in the Iron Quadrangle region, a prolific greenstone belt near the city of Belo Horizonte in the state of Minas Gerais, Brazil. Jaguar controls 27,357 hectares of mineral concessions in this…

VIEW PROJECT

Dona Lake DSR

Serving on Newmont Goldcorp’s Tailings Independent Review Board, Tierra Group provided an Independent Dam Safety Review for the Dona Lake Mine tailings storage facility in Pickle Lake, Ontario, Canada.

VIEW PROJECT

Los Gatos Project

TSF Design and CQA Tierra Group provided detailed Stage 1 and 2 Tailings Storage Facility design, conducted a process plant geotechnical foundation investigation, and provided Construction Quality Assurance for Sunshine Silver Mining's Los Gatos Project in Chihuahua, Mexico. Tierra Group then…

VIEW PROJECT

Black Butte Copper Project

Tierra Group performed an independent engineering design review of a Cemented Tailings Facility (CTF) and multiple processes and freshwater ponds. Tailings will be mixed with cement at the paste plant and deposited in the CTF along with underground mine development…

VIEW PROJECT

Tajo Crimea Project

Tierra Group evaluated the Tajo Crimea Pit’s geotechnical and hydrogeological characteristics to determine in-pit tailings storage feasibility. The project scope defined geotechnical and hydrogeologic site conditions through field investigations and in-situ pump testing. Tierra Group developed a 3D groundwater model…

VIEW PROJECT

Bunker Hill

Dry Stack Tailings Storage Facility Tierra Group designed a dry stack TSF to store excess tailings from the underground paste backfill. The dry stack TSF was challenging, given the limited land area, steep terrain, seasonal cold weather, and surface water…

VIEW PROJECT

Jerritt Canyon Mine

2023 Dam Inspections/Review Tierra Group completed a site visit to inspect three tailings storage facilities (TSFs) and the Evaporation Pond. In addition to the site visit and dam inspections, design and monitoring reports (prepared by others) were reviewed for each…

VIEW PROJECT

Rosario Mine

Tierra Group performed a Dam Safety Review (DSR) including geotechnical investigations and seepage and slope stability analyses for a 20-m high TSF at this 300‑tpd underground polymetallic mine. The audit was prepared following the Mt. Polley tailings dam failure in…

VIEW PROJECT

Douglas County Public Works

Tierra Group updated the County’s Standard Operating Procedures (SOPs) for Municipal Operations to maintain the County’s compliance with the requirements for stormwater discharges from the County’s municipal separate storm sewer system (MS4) under the Colorado Discharge Permit System (CDPS). Tierra…

VIEW PROJECT

Peñasquito

Tierra Group was selected to assist Goldcorp with global Tailings Stewardship Strategy (TSS) implementation at all of Goldcorp’s active tailings sites in Latin America (Mexico, Argentina, and Guatemala). Tierra Group worked in conjunction with Goldcorp and another global engineering consulting…

VIEW PROJECT

Robinson Mine

Robinson Mine Tailings Impoundment Audit Prior to joining Tierra Group, our Team completed a third-party tailings impoundment audit. The audit included reviewing operational procedures, monitoring, design, and future tailings storage planning. Produced an audit report for company’s internal use. (Tetra Tech,…

VIEW PROJECT