Glencore’s Antapaccay mine is located in the Espinar province, Cuzco, Perú. Tierra Group logged geotechnical, geological and geo-mechanical properties of drill core advanced in Antapaccay's Northern Pit. Approximately 6,000 meters of core were logged. Specific samples were selected for geotechnical testing to measure rock and shear strength parameters. Information obtained in the field and laboratory were used to modify the pit slope design. The project lasted 7 months utilizing a 22-person Tierra Group crew.
Don Mario Mine is an open pit gold/copper mine located in the Chiquitos Province, Santa Cruz, Bolivia that has been operating since 2002 and currently produces 2700 tpd mill throughput. Conventional tailings are transported and deposited in a high-density polyethylene lined geomembrane valley…
Hollister Waste Rock Facility Storage Tierra Group performed a third-party peer review of a Waste Rock Storage Facility (WRSF) design at Klondex Mines’ (Klondex) Hollister Mine in northern Nevada. The WRSF, as designed, involved lining the mine’s existing West Pit…
Tierra Group developed a site-wide water management plan, and performed a liquefaction potential study following the Samarco tailings dam failure in Minas Gerais, Brazil. A tailings storage facility water balance was developed to optimize water usage and minimize risks at…
Tierra Group has a history of annually providing third-party technical reviews for the tailings storage facility and heap leach facility at Anagold's Çöpler Gold Mine in Middle Anatolia, Turkey. Additionally, Tierra Group currently performs independent technical reviews for the rockfill…
Robinson Mine Tailings Impoundment Audit Prior to joining Tierra Group, our Team completed a third-party tailings impoundment audit. The audit included reviewing operational procedures, monitoring, design, and future tailings storage planning. Produced an audit report for company’s internal use. (Tetra Tech,…
Tierra Group performed an independent technical peer review of the Boleo Mine’s operating tailings storage facility design. In doing so Tierra Group identified several design modifications that when implemented for future stages will reduce sustaining capital cost expenditures by several…
Glencore’s Antapaccay mine is located in the Espinar province, Cuzco, Perú. Tierra Group logged geotechnical, geological and geo-mechanical properties of drill core advanced in Antapaccay's Northern Pit. Approximately 6,000 meters of core were logged. Specific samples were selected for geotechnical…
Tierra Group was selected to assist Goldcorp with global Tailings Stewardship Strategy (TSS) implementation at all of Goldcorp’s active tailings sites in Latin America (Mexico, Argentina, and Guatemala). Tierra Group worked in conjunction with Goldcorp and another global engineering consulting…
Tierra Group designed the Bunker Hill dry stack TSF. The TSF design was challenging given the limited land area, steep terrain, seasonal cold weather, and surface water management. Tierra Group’s scope of work included siting the facilities, geotechnical investigations, civil…
Tierra Group prepared a civil engineering design for SSR Mining’s Mina Pirquitas in Jujuy Province, Argentina and developed current and future water-mass balance through hydrological/hydraulics calculations and modeling. Tierra Group developed the ultimate tailings surface, deposition plan, spillway relocation analysis,…
Tierra Group performed a technical peer review of the Isabella Pearl heap leach facility (HLF) owned by Gold Resource Corporation. Isabella Pearl mine is located at the west end of the Santa Fe mining district in the Walker Lane gold…
Tierra Group performed a tailings storage facility safety (TSF) audit for the 90 m high upstream constructed tailings dam at La Negra Mine in Querétaro, Mexico. The project included a TSF dam inspection and Dam Safety Inspection Report (DSIR) containing operational…