Stibnite Gold Project

Project Highlights:

  • Tailings Storage Facility (TSF) Design
  • Geotechnical Engineering
  • Civil Engineering
  • Hydrology
  • Water Balance
  • Pre-feasibility Study
  • Water Diversions

The Stibnite project is located in the remote central Idaho Rockies near the town of Yellow Pine.  It is a brownfields gold-antimony project featuring three open pits and an anticipated 22,000 tpd plant throughput, along with challenging terrain and environmental constraints. Tierra Group completed the preliminary feasibility design for the proposed tailings storage facility, water diversions, and site-wide water management, including relevant content for the NI-43-101-compliant prefeasibility technical report. Tierra Group also completed TSF and water diversion designs and completed reclamation cost estimating for a NI 43-101 compliant feasibility study published in January 2020. Tierra Group also completed engineering analyses and design for federal and state permitting.

The TSF was lined with a composite geosynthetic liner system. A rockfill buttress was built in multiple stages during project development. Diversions redirected a perennial mountain stream around the TSF. Tierra Group continues supporting Midas by completing detailed design and permitting support.

Project Highlights:

  • Tailings Storage Facility (TSF) Design
  • Geotechnical Engineering
  • Civil Engineering
  • Hydrology
  • Water Balance
  • Pre-feasibility Study
  • Water Diversions

Similar projects

Yauricocha Mine

The Yauricocha Mine is a polymetallic (copper, lead, zinc) underground mine located in Yauyos Province, Lima, Peru. Tailings are deposited in the Yauricocha Tailings Storage Facility (TSF) located 3km from the process plant. Tierra Group was engaged in 2015 to…

VIEW PROJECT

Ernesto e Pau-a-Pique

The Ernesto e Pau-a-Pique (EPP) Mine is located in the Municipality of Pontes e Lacerda, at 440 kms west of Cuiba City, Brazil. The mine is operated by Apoena Mining, a subsidiary of Aura Minerals Inc. Tierra Group was retained…

VIEW PROJECT

Anaconda Mine

Tailings Storage Trade-Off Study Tierra Group completed trade-off studies evaluating potential TSF sites to store 25 million tonnes of tailings. Trade-off studies included dam layouts, cost estimating, and recommendations for future work. Trade-off study challenges were minimizing costs while still…

VIEW PROJECT

Hayden Operations

Tierra Group implemented a corporate Tailings Stewardship Strategy (TSS) at all of ASARCO Grupo Mexico’s mines in Arizona, USA (Hayden, Mission and Ray mines). Tierra Group conducted a site visit to each site to perform dam safety inspections, interview operations staff,…

VIEW PROJECT

Stillwater Mine

Nye-Hertzler Tailings Independent Review Panel (2020-2023) Tierra Group reviewed the TSF design to support an NI 43-101 compliant Feasibility Study. The TSF design incorporated a paste tailings disposal method in an environmentally sensitive fisheries habitat. Tierra Group sits on the Independent Review…

VIEW PROJECT

Copperstone Project

Tierra Group International, Ltd. participated as the geotechnical lead engineering firm for the Copperstone Project Pre-Feasibility Study (PFS) in Arizona, U.S.A. Tierra Group was responsible for tailings and waste rock storage, water management and underground geotechnics design and cost estimates…

VIEW PROJECT

Mexican Hat PEA Update

Tierra Group conducted an update of the Mexican Hat Project’s Preliminary Economic Assessment. Tierra Group’s update included the heap leach facility design and preliminary stacking plan, waste rock storage pad, and crushed rock storage pad design.

VIEW PROJECT

Turmalina Complex

Tierra Group developed a site-wide water management plan to improve operational water usage and management at Jaguar Mining's Turmalina Complex in Minas Gerais, Brazil. Turmalina is a zero-discharge facility that required optimizing tailings supernatant usage in the process, enhanced evaporation…

VIEW PROJECT

AranzazĂș Mine

The Aranzazú Mine is a copper-gold-silver mine located in the northeastern region of Zacatecas, Mexico. The mine includes both open pit and underground operations. The mill currently processes 2,600 tonnes of ore per day. Tierra Group finalized the geotechnical investigation…

VIEW PROJECT

Pierina Mine

Barrick Gold Corporation’s Pierina Mine in Ancash Department, Perú began operations in 1998. A progressive reclamation and closure plan began in 2013.  In 2015-16 Tierra Group developed detailed engineering designs for channels, sediment traps, two 45,000 m3 sediment ponds, water…

VIEW PROJECT

Boleo Mine

Tierra Group performed an independent technical peer review of the Boleo Mine’s operating tailings storage facility design. In doing so Tierra Group identified several design modifications that when implemented for future stages will reduce sustaining capital cost expenditures by several…

VIEW PROJECT

Cosmo Howley

Newmarket Gold’s Cosmo Howley Project Area (CHPA) is a gold mine in the Northern Territory (NT), Australia. An underground mine is currently in operation with planned underground expansion. CHPA contains several legacy open pits, waste rock dumps, and surface water…