Tierra Group developed a site-wide water management plan, and performed a liquefaction potential study following the Samarco tailings dam failure in Minas Gerais, Brazil. A tailings storage facility water balance was developed to optimize water usage and minimize risks at the site. Several water management strategies were recommended including enhanced evaporation methods, water reuse and treatment to manage potential process water shortages. A tailings liquefaction potential study assisted Jaguar in their tailings handling activities which includes "farming" pre-deposited tailings to increase tailings storage capacities at several of their tailings storage facilities.

Project Highlights:

  • Water Management
  • Water Balance
  • Water Treatment
  • Tailings Storage Evaluation

Similar projects

La Trinidad

Tierra Group began work at La Trinidad providing heap leach pad construction recommendations and a water balance. Tierra Group continued support with a heap leach pad expansion design, slope stability analyses, hydrologic analyses, diversion design, liner design, and leach solution…

VIEW PROJECT

Goldstrike Mine

Engineer of Record Barrick’s Goldstrike Mine processes 30,000 tons of gold ore per day from its combined open-pit/underground operations located in the historic Carlin Trend in Nevada, U.S.A. Goldstrike’s tailings are stored in the North Block Tailings Disposal Facility (NBTDF).…

VIEW PROJECT

Fire Creek Mine

The Fire Creek Mine, located in north-central Nevada, is owned and operated by Klondex Gold & Silver Mining Company.  The mine is an underground mine that is operating a bulk sampling program and has recently submitted its Preliminary Feasibility Study. As…

VIEW PROJECT

Goldfield Bonanza Project

Lode-Star Gold, Inc., in advance of their proposed mining operations, submited a Physical Separation Facility application with the State of Nevada for their Goldfield Bonanza Project located in Esmeralda County, Nevada. The mine, located in the historic high-grade gold-bearing district of…

VIEW PROJECT

Tajo Crimea Project

Tierra Group evaluated the Tajo Crimea Pit’s geotechnical and hydrogeological characteristics to determine in-pit tailings storage feasibility. The project scope defined geotechnical and hydrogeologic site conditions through field investigations and in-situ pump testing. Tierra Group developed a 3D groundwater model…

VIEW PROJECT

Brushy Creek 2

Tierra Group was commissioned by Doe Run to design a new tailings storage facility at the Brushy Creek Mine. Tierra Group completed a geotechnical investigation including boring, classifying, and sampling soil and rock. Trade-off studies were performed to minimize construction…

VIEW PROJECT

Aranzazú Mine

The Aranzazú Mine is a copper-gold-silver mine located in the northeastern region of Zacatecas, Mexico. The mine includes both open pit and underground operations. The mill currently processes 2,600 tonnes of ore per day. Tierra Group finalized the geotechnical investigation…

VIEW PROJECT

Gediktepe Peer Review

Tierra Group provided technical direction and review of the Gediktepe Heap Leach Facility (HLF), ponds, and waste rock dump facility designs. Tierra Group will also provide CQA review during HLF construction.

VIEW PROJECT

Bunker Hill

Dry Stack Tailings Storage Facility Tierra Group designed a dry stack TSF to store excess tailings from the underground paste backfill. The dry stack TSF was challenging, given the limited land area, steep terrain, seasonal cold weather, and surface water…

VIEW PROJECT

Tonopah Flats | Tailings Storage Facility

Tierra Group assisted with developing tailings disposal alternatives.

VIEW PROJECT

Pierina Mine

Barrick Gold Corporation’s Pierina Mine in Ancash Department, Perú began operations in 1998. A progressive reclamation and closure plan began in 2013.  In 2015-16 Tierra Group developed detailed engineering designs for channels, sediment traps, two 45,000 m3 sediment ponds, water…

VIEW PROJECT

Terronera Project

Hydrogeologic Characterization Tierra Group provided hydrogeological support for data characterization and developed a conceptual and groundwater model to evaluate mine water inflows and the associated groundwater drawdown due to mine dewatering activities. Water Management Technical Review Tierra Group provided a…