Tajo Crimea Project

Project Highlights:

  • Geotechnical Evaluation
  • Hydrogeological Evaluation
  • Tailings Storage Facility
  • Construction Quality Assurance

Tierra Group evaluated the Tajo Crimea Pit’s geotechnical and hydrogeological characteristics to determine in-pit tailings storage feasibility. The project scope defined geotechnical and hydrogeologic site conditions through field investigations and in-situ pump testing.

Tierra Group developed a 3D groundwater model to evaluate the potential interaction between tailings supernatant and groundwater. Following the Feasibility Study, Tierra Group completed an alternatives analysis comparing in-pit tailings storage with the Stage 7 Esperanza TSF expansion.

Tierra Group provided CQA and field engineering services during the diversion channel construction.

Project Highlights:

  • Geotechnical Evaluation
  • Hydrogeological Evaluation
  • Tailings Storage Facility
  • Construction Quality Assurance

Similar projects

El Aguila

Tierra Group performed a 3rd party engineering design peer review of a tailings storage facility expansion design. The review resulted in the owner realizing $650,000 in cost savings without compromising the facility's design integrity over the original design. Tierra Group also…

VIEW PROJECT

Dam Assessment

Tierra Group performed a site visit and visual inspection of a dam to assess its overall condition and provide the Owner recommendations for continued maintenance, monitoring, and improvements. The assessment was a follow-up to previous work completed by Tierra Group…

VIEW PROJECT

Big Ledge Mine

Tierra Group developed a water balance model to track flows into a backfilled pit at the closed Big Ledge Mine Barite Operation near Wells, Nevada. The Model was used to determine pipeline sizing to a remote treatment pond that is…

VIEW PROJECT

NioCorp’s Elk Creek | Tailings Storage Facility (TSF) Feasibility Study

Tierra Group advanced the TSF design to a Feasibility Level according to the Canadian National Instrument NI 43-101 and the U.S. Security and Exchange Commission’s Subpart SK-1300 regulation. Tierra Group’s scope of work included a geotechnical investigation, engineering analysis, and TSF…

VIEW PROJECT

Pirquitas Tailings Review

Tierra Group prepared a civil engineering design for SSR Mining’s Mina Pirquitas in Jujuy Province, Argentina and developed current and future water-mass balance through hydrological/hydraulics calculations and modeling. Tierra Group developed the ultimate tailings surface, deposition plan, spillway relocation analysis,…

VIEW PROJECT

Bunker Hill | Tailings Storage Facility (TSF) Design

Tierra Group designed the Bunker Hill dry stack TSF. The TSF design was challenging given the limited land area, steep terrain, seasonal cold weather, and surface water management. Tierra Group’s scope of work included siting the facilities, geotechnical investigations, civil…

VIEW PROJECT

La Negra Mine

Tierra Group performed a tailings storage facility safety (TSF) audit for the 90 m high upstream constructed tailings dam at La Negra Mine in Querétaro, Mexico. The project included a TSF dam inspection and Dam Safety Inspection Report (DSIR) containing operational…

VIEW PROJECT

Santa Pancha Mine

Tierra Group provided a desktop and field review of B2Gold’s Santa Pancha Mine hydrogeology. The review identified data gaps in site data and provided recommendations for improve an existing site hydrogeology model and improve underground water management. The hydrogeologic model…

VIEW PROJECT

Stibnite Gold Project

The Stibnite project is located in the remote central Idaho Rockies near the town of Yellow Pine.  It is a brownfields gold-antimony project featuring three open pits and an anticipated 22,000 tpd plant throughput, along with challenging terrain and environmental…

VIEW PROJECT

Rhyolite Ridge

Tierra Group is providing water management and geotechnical engineering services to support a Preliminary Feasibility Study at the Rhyolite Ridge Lithium Mine Project in Nevada.

VIEW PROJECT

2020 TSF Annual Dam Inspection

Tierra Group completed an annual dam safety inspection (DSI) to meet both Nevada Division of Water Resources (NDWR) Dam Safety and the client's requirements. The DSI included reviewing monitoring data, a dam and appurtenant structures inspection, and a DSI report.

VIEW PROJECT

Palmarejo Mine

Tierra Group performed an initial site visit to Coeur Mining’s Palmarejo Mine to conduct dam safety inspections of the tailings storage facility, environmental control dam, water diversion dam, and water diversion channel. Prior to the site visit, Tierra Group reviewed…

VIEW PROJECT