Project Highlights:

  • Independent Engineering Review
  • Tailings Storage Facilities
  • Tailings Assurance Audit

Tailings Management Assurance Review

Tierra Group served as the Lead Auditor and conducted MARs for the TSFs at this confidential project. Tierra Group reviewed all available facility documentation, including OMS Manuals, EAPs, design reports, As-Built Reports, annual inspection reports, and other relevant documentation in determining each site’s compliance with the Company’s Tailings and Heap Leach Management Standard.

Independent Engineer's Review

Tierra Group personnel served as the Audit Lead to review tailings management procedures and compared them to standards outlined in the Company’s Corporate Tailings and Heap Leach Management Standard.

Tailings Assurance Audit

Tierra Group completed a Tailings Assurance Audit (TAA) for Tailings Storage Facility 2 (TSF2). The TAA was completed to ensure the TSF and site operations complied with the Company’s Tailings Management Standard, which closely mirrors Global Industry Standard on Tailings Management (GISTM) requirements. 

Project Highlights:

  • Independent Engineering Review
  • Tailings Storage Facilities
  • Tailings Assurance Audit

Similar projects

Hod Mine Waste Dump and Surface Water Management Design

Tierra Group provided design review and technical direction at Hod Mine in the Artvin Province of Turkey. Work included detailed design of potentially acid generating and non-acid generating waste dump facilities, their appurtenant structures and stormwater management design for the…

VIEW PROJECT

Hollister Waste Rock Facility

Hollister Waste Rock Facility Storage Tierra Group performed a third-party peer review of a Waste Rock Storage Facility (WRSF) design at Klondex Mines’ (Klondex) Hollister Mine in northern Nevada. The WRSF, as designed, involved lining the mine’s existing West Pit…

VIEW PROJECT

Dam Low Level Outlet Replacement

Tierra Group completed a geotechnical investigation, which included overseeing hollow stem auger (HSA) drilling and laboratory testing, that characterized the existing earthen dam. Tierra Group completed a low-level outlet structure design that was believed to have been compromised by internal…

VIEW PROJECT

Peñasquito

Tierra Group was selected to assist Goldcorp with global Tailings Stewardship Strategy (TSS) implementation at all of Goldcorp’s active tailings sites in Latin America (Mexico, Argentina, and Guatemala). Tierra Group worked in conjunction with Goldcorp and another global engineering consulting…

VIEW PROJECT

Tennessee Mines

Tierra Group performed Dam Safety Reviews (DSRs) for Nyrstar’s tailings storage facilities (TSFs) located in Tennessee, United States.  Tierra Group served as the Tailings Reviewer to ensure conformity with local regulations, the Nyrstar Tailings Storage Facility (TSF) Standard, and to…

VIEW PROJECT

Empire State Mine

Dam Breach Analyses Tierra Group prepared a DBA to evaluate potential downstream impacts due to a hypothetical failure (breach) in three components of Empire State Mines (ESM) tailings storage facility (TSF): North Dam (ND), South Dam (SD), and West Perimeter…

VIEW PROJECT

2020 TSF Annual Dam Inspection

Tierra Group completed an annual dam safety inspection (DSI) to meet both Nevada Division of Water Resources (NDWR) Dam Safety and the client's requirements. The DSI included reviewing monitoring data, a dam and appurtenant structures inspection, and a DSI report.

VIEW PROJECT

El Diamante Hydropower Dam

Tierra Group conducted a Preliminary Site Assessment of a potential large-scale landslide near the El Diamante Hydropower Complex in Matagalpa, Nicaragua.

VIEW PROJECT

San Andrés Mine

Previous to Tierra Group, our Team performed a geotechnical forensics assessment, which determined that spent ore from an on-off leach pad operation had liquefied causing a debris flow, which threatened inundating a major river basin. A preventative detention buttress was…

VIEW PROJECT

Tailings Review & Assurance Audit | Montana

Tailings Management Assurance Review Tierra Group served as the Lead Auditor and conducted MARs for the TSFs at this confidential project. Tierra Group reviewed all available facility documentation, including OMS Manuals, EAPs, design reports, As-Built Reports, annual inspection reports, and other…

VIEW PROJECT

North Mara Mine | Tailings Assurance Audit

Tierra Group completed a TAA for the North Mara Tailings Storage Facility (TSF). The TAA was completed to ensure the TSF and site operations complied with Barrick’s Tailings Management Standard, which closely mirrors the Global Industry Standard on Tailings Management (GISTM)…

VIEW PROJECT

Isabella Pearl

Tierra Group performed a technical peer review of the Isabella Pearl heap leach facility (HLF) owned by Gold Resource Corporation. Isabella Pearl mine is located at the west end of the Santa Fe mining district in the Walker Lane gold…