Isabella Pearl

Project Highlights:

  • Heap Leach Pad Design Peer Review
  • Slope Stability Analysis
  • Heap Leach Facility Expansion
  • Permitting Support
  • Geotechnical Investigation

Tierra Group performed a technical peer review of the Isabella Pearl heap leach facility (HLF) owned by Gold Resource Corporation. Isabella Pearl mine is located at the west end of the Santa Fe mining district in the Walker Lane gold belt about 6 miles northeast of Luning, Nevada, in Mineral County. The HLF will have a nominal throughput of 8,000 tons per day over a period of 15 months following of pre-production development and construction. Tierra Group performed the review with the following objectives:

  • Peer review the existing engineering design and drawings to ensure the proposed engineering design is adequate and in conformity with accepted engineering practices;
  • Identify opportunities to “optimize” the design to potentially reduce capital or operating costs; and
  • Identify associated risks (regulatory, financial, construction schedule, etc.) with implementing optimization.

Tierra Group identified a number of optimization opportunities and provided design enhancement recommendations to potentially reduce capital or operation costs.

Expansion Pit Slope Review

Tierra Group conducted an expansion pit slope review that included a technical memorandum of site observations/investigation, a review of past and new data, a basic slope analyses that developed recommendations for slope angles that determined if the Pit Expansion would be stable, and provided suggestions for a slope monitoring program.

HLF Phase 2A Engineering Design Change (EDC)

Tierra Group prepared an EDC to increase the permitted storage height of the existing HLF. A geotechnical field investigation and stability analysis for the Phase 2A and 3 expansion were also completed. Analysis results guided the civil grading and engineering design for each phase.

Project Highlights:

  • Heap Leach Pad Design Peer Review
  • Slope Stability Analysis
  • Heap Leach Facility Expansion
  • Permitting Support
  • Geotechnical Investigation

Similar projects

Mt. Todd Dam Assessment

Tierra Group conducted an Independent Technical review of Vista Gold Corp’s Mt. Todd Tailings Storage Facility Expansion in Northern Territory, Australia.

VIEW PROJECT

Anglo American Quellaveco Mine | Perú

Tierra Group supervised a geotechnical and hydrogeologic drilling investigation program at Anglo American’s Quellaveco Mine in the Moquegua Region of Peru. Geotechnical Investigation Tierra Group developed a geotechnical and hydrogeological research plan within and near the Quellaveco Pit footprint. This…

VIEW PROJECT

Brushy Creek 2

Tierra Group was commissioned by Doe Run to design a new tailings storage facility at the Brushy Creek Mine. Tierra Group completed a geotechnical investigation including boring, classifying, and sampling soil and rock. Trade-off studies were performed to minimize construction…

VIEW PROJECT

Mexican Hat PEA Update

Tierra Group conducted an update of the Mexican Hat Project’s Preliminary Economic Assessment. Tierra Group’s update included the heap leach facility design and preliminary stacking plan, waste rock storage pad, and crushed rock storage pad design.

VIEW PROJECT

Yauricocha Mine

The Yauricocha Mine is a polymetallic (copper, lead, zinc) underground mine located in Yauyos Province, Lima, Peru. Tailings are deposited in the Yauricocha Tailings Storage Facility (TSF) located 3km from the process plant. Tierra Group was engaged in 2015 to…

VIEW PROJECT

2020 TSF Annual Dam Inspection

Tierra Group completed an annual dam safety inspection (DSI) to meet both Nevada Division of Water Resources (NDWR) Dam Safety and the client's requirements. The DSI included reviewing monitoring data, a dam and appurtenant structures inspection, and a DSI report.

VIEW PROJECT

American Gypsum

American Gypsum Pit Planning and Support Tierra Group began working at American Gypsum’s Eagle-Gypsum mine located in Gypsum, Colorado in 2014 evaluating haul road improvements. A trade-off study provided a tool for American Gypsum to evaluate safety improvements including alternative haul road…

VIEW PROJECT

Dam Assessment

Tierra Group performed a site visit and visual inspection of a dam to assess its overall condition and provide the Owner recommendations for continued maintenance, monitoring, and improvements. The assessment was a follow-up to previous work completed by Tierra Group…

VIEW PROJECT

Ernesto e Pau-a-Pique

The Ernesto e Pau-a-Pique (EPP) Mine is located in the Municipality of Pontes e Lacerda, at 440 kms west of Cuiba City, Brazil. The mine is operated by Apoena Mining, a subsidiary of Aura Minerals Inc. Tierra Group was retained…

VIEW PROJECT

Pirquitas Tailings Review

Tierra Group prepared a civil engineering design for SSR Mining’s Mina Pirquitas in Jujuy Province, Argentina and developed current and future water-mass balance through hydrological/hydraulics calculations and modeling. Tierra Group developed the ultimate tailings surface, deposition plan, spillway relocation analysis,…

VIEW PROJECT

San Andrés Mine

Previous to Tierra Group, our Team performed a geotechnical forensics assessment, which determined that spent ore from an on-off leach pad operation had liquefied causing a debris flow, which threatened inundating a major river basin. A preventative detention buttress was…

VIEW PROJECT

Tennessee Mines

Tierra Group performed Dam Safety Reviews (DSRs) for Nyrstar’s tailings storage facilities (TSFs) located in Tennessee, United States.  Tierra Group served as the Tailings Reviewer to ensure conformity with local regulations, the Nyrstar Tailings Storage Facility (TSF) Standard, and to…

VIEW PROJECT