Tierra Group conducted an update of the Mexican Hat Project’s Preliminary Economic Assessment. Tierra Group’s update included the heap leach facility design and preliminary stacking plan, waste rock storage pad, and crushed rock storage pad design.
Lode-Star Gold, Inc., in advance of their proposed mining operations, submited a Physical Separation Facility application with the State of Nevada for their Goldfield Bonanza Project located in Esmeralda County, Nevada. The mine, located in the historic high-grade gold-bearing district of…
Tierra Group was selected to assist Goldcorp with global Tailings Stewardship Strategy (TSS) implementation at all of Goldcorp’s active tailings sites in Latin America (Mexico, Argentina, and Guatemala). Tierra Group worked in conjunction with Goldcorp and another global engineering consulting…
Tierra Group performed an independent engineering design review of a Cemented Tailings Facility (CTF) and multiple processes and freshwater ponds. Tailings will be mixed with cement at the paste plant and deposited in the CTF along with underground mine development…
Tierra Group supported proposed Rapid Infiltration Basins Geotechnical Investigation at Au-reka Gold Corporation’s Cove Project in Nevada. Investigation included borehole drilling, test pits, infiltration testing and permeability testing.
Heap Leach Procurement & Construction Quality Assurance Tierra Group provided Issued for Construction (IFC) design drawings and specifications for procurement requirements for the expansion of the Camino Rojo HLF. Information required included liner specifications, drainage collection piping, and quantities. Additionally,…
Tierra Group performed a 3rd party engineering design peer review of a tailings storage facility expansion design. The review resulted in the owner realizing $650,000 in cost savings without compromising the facility's design integrity over the original design. Tierra Group also…
Dam Breach Analyses Tierra Group prepared a DBA to evaluate potential downstream impacts due to a hypothetical failure (breach) in three components of Empire State Mines (ESM) tailings storage facility (TSF): North Dam (ND), South Dam (SD), and West Perimeter…
Tierra Group completed an annual dam safety inspection (DSI) to meet both Nevada Division of Water Resources (NDWR) Dam Safety and the client's requirements. The DSI included reviewing monitoring data, a dam and appurtenant structures inspection, and a DSI report.
Tierra Group performed a Hazard and Operability review (HAZOP) for the new Cobalt Pilot Pant located at the Madison Mine facility in Missouri.
The Aurora Mine Mill Facility (previously Esmeralda Mill) is located in the historic Aurora mining district of the eastern Sierra Nevada Mountain Range in Nevada, USA. Aurora recently, with the support of Tierra Group completed a Minor Modification to the…
Tierra Group provides Tailings Stewardship Services for the Marlin Mine Tailings Storage Facility. Tierra Group performed a 5-year Dam Safety Review consistent with the Canadian Dam Association protocols, a Facilitated Risk Assessment, site training and in depth inspections of management…
TSF Design and CQA Tierra Group provided detailed Stage 1 and 2 Tailings Storage Facility design, conducted a process plant geotechnical foundation investigation, and provided Construction Quality Assurance for Sunshine Silver Mining's Los Gatos Project in Chihuahua, Mexico. Tierra Group then…