Masbate Mine

Project Highlights:

  • Forensics Analysis
  • Due Diligence
  • Mine Plan Optimization
  • Water Management
  • Water Treatment

Tierra Group performed a study of Masbate’s 12-Mt tailings storage facility. Services provided included a forensic study to determine the cause of seepage through an abutment and performed an independent safety audit of tailings management practices. A risk analysis was performed and water management optimization recommendations were made. Tierra Group and its sub-consultants then designed and commissioned a 15,000-m3/d supernatant water treatment plant. The water treatment plant was commissioned in early 2015 and has run continuously at 90 to 95% efficiency, greatly improving the mine’s site-wide water balance.

Project Highlights:

  • Forensics Analysis
  • Due Diligence
  • Mine Plan Optimization
  • Water Management
  • Water Treatment

Similar projects

Tajo Crimea Project

Tierra Group evaluated the Tajo Crimea Pit’s geotechnical and hydrogeological characteristics to determine in-pit tailings storage feasibility. The project scope defined geotechnical and hydrogeologic site conditions through field investigations and in-situ pump testing. Tierra Group developed a 3D groundwater model…

VIEW PROJECT

Bald Mountain Mine

Tierra Group assisted the Bald Mountain Mine Project Development Team with an evaluation of potential uses for spent ore on legacy heap leach facilities. Tierra Group completed a collaborative trade-off study with site personnel evaluating spent ore use as overliner…

VIEW PROJECT

Ernesto e Pau-a-Pique

The Ernesto e Pau-a-Pique (EPP) Mine is located in the Municipality of Pontes e Lacerda, at 440 kms west of Cuiba City, Brazil. The mine is operated by Apoena Mining, a subsidiary of Aura Minerals Inc. Tierra Group was retained…

VIEW PROJECT

Camino Rojo Heap Leach Design

Tierra Group provided a heap leach facility detailed design (for construction), procurement, CQA and project management for the Camino Rojo Mine in Zacatecas, Mexico.

VIEW PROJECT

Tennessee Mines

Tierra Group performed Dam Safety Reviews (DSRs) for Nyrstar’s tailings storage facilities (TSFs) located in Tennessee, United States.  Tierra Group served as the Tailings Reviewer to ensure conformity with local regulations, the Nyrstar Tailings Storage Facility (TSF) Standard, and to…

VIEW PROJECT

Caeté Complex

Tierra Group developed a site-wide water management plan, and performed a liquefaction potential study following the Samarco tailings dam failure in Minas Gerais, Brazil. A tailings storage facility water balance was developed to optimize water usage and minimize risks at…

VIEW PROJECT

Dam Low Level Outlet Replacement

Tierra Group completed a geotechnical investigation, which included overseeing hollow stem auger (HSA) drilling and laboratory testing, that characterized the existing earthen dam. Tierra Group completed a low-level outlet structure design that was believed to have been compromised by internal…

VIEW PROJECT

Karouni Mine

Tierra Group reviewed and provided pit slope recommendations and conducted hydrological assessments for the Resource 1 and 2 deposits water management system at Troy Resources’ Karouni Mine (Karouni). Advanced pre-feasibility level recommendations for pit development were provided based on benchmarking…

VIEW PROJECT

El Diamante Hydropower Dam

Tierra Group conducted a Preliminary Site Assessment of a potential large-scale landslide near the El Diamante Hydropower Complex in Matagalpa, Nicaragua.

VIEW PROJECT

Goldfield Bonanza Project

Lode-Star Gold, Inc., in advance of their proposed mining operations, submited a Physical Separation Facility application with the State of Nevada for their Goldfield Bonanza Project located in Esmeralda County, Nevada. The mine, located in the historic high-grade gold-bearing district of…

VIEW PROJECT

Goldstrike Mine

Engineer of Record Barrick’s Goldstrike Mine processes 30,000 tons of gold ore per day from its combined open-pit/underground operations located in the historic Carlin Trend in Nevada, U.S.A. Goldstrike’s tailings are stored in the North Block Tailings Disposal Facility (NBTDF).…

VIEW PROJECT

Gediktepe Peer Review

Tierra Group provided technical direction and review of the Gediktepe Heap Leach Facility (HLF), ponds, and waste rock dump facility designs. Tierra Group will also provide CQA review during HLF construction.

VIEW PROJECT