Stibnite Gold Project

Project Highlights:

  • Tailings Storage Facility (TSF) Design
  • Geotechnical Engineering
  • Civil Engineering
  • Hydrology
  • Water Balance
  • Pre-feasibility Study
  • Water Diversions

The Stibnite project is located in the remote central Idaho Rockies near the town of Yellow Pine.  It is a brownfields gold-antimony project featuring three open pits and an anticipated 22,000 tpd plant throughput, along with challenging terrain and environmental constraints. Tierra Group completed the preliminary feasibility design for the proposed tailings storage facility, water diversions, and site-wide water management, including relevant content for the NI-43-101-compliant prefeasibility technical report. Tierra Group also completed TSF and water diversion designs and completed reclamation cost estimating for a NI 43-101 compliant feasibility study published in January 2020. Tierra Group also completed engineering analyses and design for federal and state permitting.

The TSF was lined with a composite geosynthetic liner system. A rockfill buttress was built in multiple stages during project development. Diversions redirected a perennial mountain stream around the TSF. Tierra Group continues supporting Midas by completing detailed design and permitting support.

Project Highlights:

  • Tailings Storage Facility (TSF) Design
  • Geotechnical Engineering
  • Civil Engineering
  • Hydrology
  • Water Balance
  • Pre-feasibility Study
  • Water Diversions

Similar projects

Los Filos Mine

Tierra Group was selected to assist Goldcorp with global Tailings Stewardship Strategy (TSS) implementation at all of Goldcorp’s active tailings sites in Latin America (Mexico, Argentina, and Guatemala). Tierra Group worked in conjunction with Goldcorp and another global engineering consulting…

VIEW PROJECT

San Albino Dry Stack Tailings Storage Facility Design

Tierra Group supported construction of the San Albino Mine in Nueva Segovia, Nicaragua. Tierra Group designed a dry stack drum filtered-tailings storage facility. A siting study optimized the dry stack location and minimized CAPEX and OPEX. Tierra Group developed a site-wide water…

VIEW PROJECT

Fekola Project | Mali

Earthworks & Construction Quality Control (CQC) Services Tierra Group provided earthworks and concrete Construction Quality Control (CQC) services for B2Gold's Fekola Mine in western Mali. Tierra Group overcame the remote location and kept a dedicated team on-site throughout the 2-year…

VIEW PROJECT

Karouni Mine

Tierra Group reviewed and provided pit slope recommendations and conducted hydrological assessments for the Resource 1 and 2 deposits water management system at Troy Resources’ Karouni Mine (Karouni). Advanced pre-feasibility level recommendations for pit development were provided based on benchmarking…

VIEW PROJECT

Santa Pancha Mine

Tierra Group provided a desktop and field review of B2Gold’s Santa Pancha Mine hydrogeology. The review identified data gaps in site data and provided recommendations for improve an existing site hydrogeology model and improve underground water management. The hydrogeologic model…

VIEW PROJECT

Cove Project RIB Geotechnical Investigation

Tierra Group supported proposed Rapid Infiltration Basins Geotechnical Investigation at Au-reka Gold Corporation’s Cove Project in Nevada. Investigation included borehole drilling, test pits, infiltration testing and permeability testing.

VIEW PROJECT

Bolivar Mine

The Bolivar mine is a 3,000 tonne per day underground mining operation in Chihuahua, Mexico producing copper, zinc, silver, and gold. Space constraints in mountainous terrain require dewatering tailings to reduce required area for tailings storage. Tierra Group is assisting…

VIEW PROJECT

Dam Assessment

Tierra Group performed a site visit and visual inspection of a dam to assess its overall condition and provide the Owner recommendations for continued maintenance, monitoring, and improvements. The assessment was a follow-up to previous work completed by Tierra Group…

VIEW PROJECT

Newcrest Telfer Tailings Stewardship

Tierra Group provided Tailings Stewardship Services for TSFs and water dams at the Cadia, Terfer, and Red Chris properties. Responsibilities included data/report review; identifying and assisting the client with managing risks, liabilities, controls, and reporting; evaluating progress towards GISTM compliance;…

VIEW PROJECT

Dam Low Level Outlet Replacement

Tierra Group completed a geotechnical investigation, which included overseeing hollow stem auger (HSA) drilling and laboratory testing, that characterized the existing earthen dam. Tierra Group completed a low-level outlet structure design that was believed to have been compromised by internal…

VIEW PROJECT

El Diamante Hydropower Dam

Tierra Group conducted a Preliminary Site Assessment of a potential large-scale landslide near the El Diamante Hydropower Complex in Matagalpa, Nicaragua.

VIEW PROJECT

Tennessee Mines

Tierra Group performed Dam Safety Reviews (DSRs) for Nyrstar’s tailings storage facilities (TSFs) located in Tennessee, United States.  Tierra Group served as the Tailings Reviewer to ensure conformity with local regulations, the Nyrstar Tailings Storage Facility (TSF) Standard, and to…

VIEW PROJECT